Project Update of 500 TPD Demonstration Plant for Coal-fired Power Plant
Southern Company and MHI successfully started the world's largest 500 TPD carbon capture plant for a coal-fired power plant in June 2011 at Alabama Power's Plant Barry and achieved full load operation. These operation experience and lessons & learned of the actual plants would help fac...
Saved in:
Published in: | Energy procedia 2013, Vol.37, p.6248-6255 |
---|---|
Main Authors: | , , , , , , , , |
Format: | Article |
Language: | English |
Subjects: | |
Citations: | Items that cite this one |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | Southern Company and MHI successfully started the world's largest 500 TPD carbon capture plant for a coal-fired power plant in June 2011 at Alabama Power's Plant Barry and achieved full load operation. These operation experience and lessons & learned of the actual plants would help facilitate scale-up CO2 capture plant for coal fired power plant. This paper gives updated operation results of the demonstration plant along with MHI's R&D Activities for the commercial application |
---|---|
ISSN: | 1876-6102 1876-6102 |
DOI: | 10.1016/j.egypro.2013.06.553 |