Fuzzy multi-objective modeling of project scheduling with multi-skill resource constraints with the ability to change the level of skills and interrupt activities

Purpose: Time and cost are significant factors in every project. By reducing the resources allocated to the project, project costs are reduced, while the reduction of available resources means the inability to simultaneously implement activities or activities in the shortest possible time, which in...

Full description

Saved in:
Bibliographic Details
Published in:Mudīrīyyat-i tawlīd va ʻamalīyyāt 2023-03, Vol.14 (1), p.1-20
Main Authors: Mojtaba Salehi, Yalda Rahimi, Shohreh Shariati
Format: Article
Language:per
Subjects:
Online Access:Get full text
Tags: Add Tag
No Tags, Be the first to tag this record!
cited_by
cites
container_end_page 20
container_issue 1
container_start_page 1
container_title Mudīrīyyat-i tawlīd va ʻamalīyyāt
container_volume 14
creator Mojtaba Salehi
Yalda Rahimi
Shohreh Shariati
description Purpose: Time and cost are significant factors in every project. By reducing the resources allocated to the project, project costs are reduced, while the reduction of available resources means the inability to simultaneously implement activities or activities in the shortest possible time, which in turn increases the duration of the project. This is although, in all projects, the completion of the projects in the earliest time is considered one of the important parameters of the project. Considering the highly practical application of the examined problem, project scheduling by investing multi-skill resources with the possibility of changing the skill level in fuzzy conditions can be considered a positive step towards creating project scheduling problems.                          Design/methodology/approach: In this paper, the proposed mathematical model of meta-heuristic genetic algorithms to solve the proposed model is discussed and explained in detail. Several skills are needed to perform each activity. The goal is to optimally determine resource availability and find the best schedule by minimizing investment in resources.               Findings: Considering the activities' need for different skills as well as the expertise of the project members in different skills, it seems obvious that each activity can be done with several different situations in terms of human resources allocation, which might be only for one activity, reaching more than 10 modes. As a result, compared to MRCPSP, this issue has a much higher complexity. The Resource Investment Problem (RIP) is a variant of RCPSP where renewable resource constraints are considered decision variables. In many projects, managers, in addition to making decisions about the time of implementation of activities, should determine the number of resources allocated to activities in each period of the implementation of activities according to the status of the project, which means ignoring the constant pattern of resource consumption for activities during their implementation.                           Practical implications: By comparing the algorithms with the indicators of maximum extension, distance from the ideal solution, distance, and several Pareto solutions, it was found that the multi-objective genetic algorithm performs far better than the multi-objective Cuckoo algorithm regarding the criteria, distance from the ideal solution, and the largest expansion. However, in terms of the number of Pareto
doi_str_mv 10.22108/pom.2023.135716.1478
format article
fullrecord <record><control><sourceid>doaj</sourceid><recordid>TN_cdi_doaj_primary_oai_doaj_org_article_4e7b1ae3b16a4f08a3ffa1ed9a187260</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><doaj_id>oai_doaj_org_article_4e7b1ae3b16a4f08a3ffa1ed9a187260</doaj_id><sourcerecordid>oai_doaj_org_article_4e7b1ae3b16a4f08a3ffa1ed9a187260</sourcerecordid><originalsourceid>FETCH-doaj_primary_oai_doaj_org_article_4e7b1ae3b16a4f08a3ffa1ed9a1872603</originalsourceid><addsrcrecordid>eNqtjltOg0AUhicmJjbaJTQ5GyjOhQJ9Njb67js5wAFOHRgyM9S0y3GlWuwSfPqTL_9NiI2SidZKFs-TGxIttUmU2eUqS1SaF3dipVNtttl-Jx_EOoSjlFLtlTapWYnvw3y5nGGYbeStq45URz4RDK4hy2MHroXJuyuGUPfUzAv94tjfMuGTrQVPwc2-JqjdGKJHHmP4c8WeACu2HM8QHdQ9jh0t1NKJ7HVgqQiAYwO_OfJ-niLg9QhHpvAk7lu0gdY3fRTvh9ePl7dt4_BYTp4H9OfSIZcLcL4r0UeuLZUp5ZVCMpXKMG1lgaZtUVGzR1XkOpPmP7t-AJI0gHQ</addsrcrecordid><sourcetype>Open Website</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype></control><display><type>article</type><title>Fuzzy multi-objective modeling of project scheduling with multi-skill resource constraints with the ability to change the level of skills and interrupt activities</title><source>DOAJ Directory of Open Access Journals</source><creator>Mojtaba Salehi ; Yalda Rahimi ; Shohreh Shariati</creator><creatorcontrib>Mojtaba Salehi ; Yalda Rahimi ; Shohreh Shariati</creatorcontrib><description>Purpose: Time and cost are significant factors in every project. By reducing the resources allocated to the project, project costs are reduced, while the reduction of available resources means the inability to simultaneously implement activities or activities in the shortest possible time, which in turn increases the duration of the project. This is although, in all projects, the completion of the projects in the earliest time is considered one of the important parameters of the project. Considering the highly practical application of the examined problem, project scheduling by investing multi-skill resources with the possibility of changing the skill level in fuzzy conditions can be considered a positive step towards creating project scheduling problems.                          Design/methodology/approach: In this paper, the proposed mathematical model of meta-heuristic genetic algorithms to solve the proposed model is discussed and explained in detail. Several skills are needed to perform each activity. The goal is to optimally determine resource availability and find the best schedule by minimizing investment in resources.               Findings: Considering the activities' need for different skills as well as the expertise of the project members in different skills, it seems obvious that each activity can be done with several different situations in terms of human resources allocation, which might be only for one activity, reaching more than 10 modes. As a result, compared to MRCPSP, this issue has a much higher complexity. The Resource Investment Problem (RIP) is a variant of RCPSP where renewable resource constraints are considered decision variables. In many projects, managers, in addition to making decisions about the time of implementation of activities, should determine the number of resources allocated to activities in each period of the implementation of activities according to the status of the project, which means ignoring the constant pattern of resource consumption for activities during their implementation.                           Practical implications: By comparing the algorithms with the indicators of maximum extension, distance from the ideal solution, distance, and several Pareto solutions, it was found that the multi-objective genetic algorithm performs far better than the multi-objective Cuckoo algorithm regarding the criteria, distance from the ideal solution, and the largest expansion. However, in terms of the number of Pareto solutions, the algorithm is not superior to the other algorithms. Therefore, it can be concluded that the multi-objective genetic algorithm has relatively a better performance than the multi-objective Cuckoo algorithm.            Social implications: In this research, each activity can be performed with several different situations in terms of human resource allocation, which may reach more than 10 situations just for one activity. As a result, compared to MRCPSP, this issue has a higher level of complexity. Literature review indicates that being multi-skilled increases the productivity, quality, and consistency of work and gives managers more flexibility in work allocation.               Originality/value: One of the most important branches of project scheduling knowledge is the problem of project scheduling with limited resources. This new concept has led to the development of one of the most general modes of scheduling problems under the title of multi-mode project scheduling with limited resources, which solves many real problems and can be modeled for application.</description><identifier>EISSN: 2423-6950</identifier><identifier>DOI: 10.22108/pom.2023.135716.1478</identifier><language>per</language><publisher>University of Isfahan</publisher><subject>meta-heuristic algorithms ; multiskilled manpower ; parameter setting ; project scheduling</subject><ispartof>Mudīrīyyat-i tawlīd va ʻamalīyyāt, 2023-03, Vol.14 (1), p.1-20</ispartof><lds50>peer_reviewed</lds50><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><link.rule.ids>314,780,784,864,2100,27923,27924</link.rule.ids></links><search><creatorcontrib>Mojtaba Salehi</creatorcontrib><creatorcontrib>Yalda Rahimi</creatorcontrib><creatorcontrib>Shohreh Shariati</creatorcontrib><title>Fuzzy multi-objective modeling of project scheduling with multi-skill resource constraints with the ability to change the level of skills and interrupt activities</title><title>Mudīrīyyat-i tawlīd va ʻamalīyyāt</title><description>Purpose: Time and cost are significant factors in every project. By reducing the resources allocated to the project, project costs are reduced, while the reduction of available resources means the inability to simultaneously implement activities or activities in the shortest possible time, which in turn increases the duration of the project. This is although, in all projects, the completion of the projects in the earliest time is considered one of the important parameters of the project. Considering the highly practical application of the examined problem, project scheduling by investing multi-skill resources with the possibility of changing the skill level in fuzzy conditions can be considered a positive step towards creating project scheduling problems.                          Design/methodology/approach: In this paper, the proposed mathematical model of meta-heuristic genetic algorithms to solve the proposed model is discussed and explained in detail. Several skills are needed to perform each activity. The goal is to optimally determine resource availability and find the best schedule by minimizing investment in resources.               Findings: Considering the activities' need for different skills as well as the expertise of the project members in different skills, it seems obvious that each activity can be done with several different situations in terms of human resources allocation, which might be only for one activity, reaching more than 10 modes. As a result, compared to MRCPSP, this issue has a much higher complexity. The Resource Investment Problem (RIP) is a variant of RCPSP where renewable resource constraints are considered decision variables. In many projects, managers, in addition to making decisions about the time of implementation of activities, should determine the number of resources allocated to activities in each period of the implementation of activities according to the status of the project, which means ignoring the constant pattern of resource consumption for activities during their implementation.                           Practical implications: By comparing the algorithms with the indicators of maximum extension, distance from the ideal solution, distance, and several Pareto solutions, it was found that the multi-objective genetic algorithm performs far better than the multi-objective Cuckoo algorithm regarding the criteria, distance from the ideal solution, and the largest expansion. However, in terms of the number of Pareto solutions, the algorithm is not superior to the other algorithms. Therefore, it can be concluded that the multi-objective genetic algorithm has relatively a better performance than the multi-objective Cuckoo algorithm.            Social implications: In this research, each activity can be performed with several different situations in terms of human resource allocation, which may reach more than 10 situations just for one activity. As a result, compared to MRCPSP, this issue has a higher level of complexity. Literature review indicates that being multi-skilled increases the productivity, quality, and consistency of work and gives managers more flexibility in work allocation.               Originality/value: One of the most important branches of project scheduling knowledge is the problem of project scheduling with limited resources. This new concept has led to the development of one of the most general modes of scheduling problems under the title of multi-mode project scheduling with limited resources, which solves many real problems and can be modeled for application.</description><subject>meta-heuristic algorithms</subject><subject>multiskilled manpower</subject><subject>parameter setting</subject><subject>project scheduling</subject><issn>2423-6950</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2023</creationdate><recordtype>article</recordtype><sourceid>DOA</sourceid><recordid>eNqtjltOg0AUhicmJjbaJTQ5GyjOhQJ9Njb67js5wAFOHRgyM9S0y3GlWuwSfPqTL_9NiI2SidZKFs-TGxIttUmU2eUqS1SaF3dipVNtttl-Jx_EOoSjlFLtlTapWYnvw3y5nGGYbeStq45URz4RDK4hy2MHroXJuyuGUPfUzAv94tjfMuGTrQVPwc2-JqjdGKJHHmP4c8WeACu2HM8QHdQ9jh0t1NKJ7HVgqQiAYwO_OfJ-niLg9QhHpvAk7lu0gdY3fRTvh9ePl7dt4_BYTp4H9OfSIZcLcL4r0UeuLZUp5ZVCMpXKMG1lgaZtUVGzR1XkOpPmP7t-AJI0gHQ</recordid><startdate>20230301</startdate><enddate>20230301</enddate><creator>Mojtaba Salehi</creator><creator>Yalda Rahimi</creator><creator>Shohreh Shariati</creator><general>University of Isfahan</general><scope>DOA</scope></search><sort><creationdate>20230301</creationdate><title>Fuzzy multi-objective modeling of project scheduling with multi-skill resource constraints with the ability to change the level of skills and interrupt activities</title><author>Mojtaba Salehi ; Yalda Rahimi ; Shohreh Shariati</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-doaj_primary_oai_doaj_org_article_4e7b1ae3b16a4f08a3ffa1ed9a1872603</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>per</language><creationdate>2023</creationdate><topic>meta-heuristic algorithms</topic><topic>multiskilled manpower</topic><topic>parameter setting</topic><topic>project scheduling</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Mojtaba Salehi</creatorcontrib><creatorcontrib>Yalda Rahimi</creatorcontrib><creatorcontrib>Shohreh Shariati</creatorcontrib><collection>DOAJ Directory of Open Access Journals</collection><jtitle>Mudīrīyyat-i tawlīd va ʻamalīyyāt</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Mojtaba Salehi</au><au>Yalda Rahimi</au><au>Shohreh Shariati</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Fuzzy multi-objective modeling of project scheduling with multi-skill resource constraints with the ability to change the level of skills and interrupt activities</atitle><jtitle>Mudīrīyyat-i tawlīd va ʻamalīyyāt</jtitle><date>2023-03-01</date><risdate>2023</risdate><volume>14</volume><issue>1</issue><spage>1</spage><epage>20</epage><pages>1-20</pages><eissn>2423-6950</eissn><abstract>Purpose: Time and cost are significant factors in every project. By reducing the resources allocated to the project, project costs are reduced, while the reduction of available resources means the inability to simultaneously implement activities or activities in the shortest possible time, which in turn increases the duration of the project. This is although, in all projects, the completion of the projects in the earliest time is considered one of the important parameters of the project. Considering the highly practical application of the examined problem, project scheduling by investing multi-skill resources with the possibility of changing the skill level in fuzzy conditions can be considered a positive step towards creating project scheduling problems.                          Design/methodology/approach: In this paper, the proposed mathematical model of meta-heuristic genetic algorithms to solve the proposed model is discussed and explained in detail. Several skills are needed to perform each activity. The goal is to optimally determine resource availability and find the best schedule by minimizing investment in resources.               Findings: Considering the activities' need for different skills as well as the expertise of the project members in different skills, it seems obvious that each activity can be done with several different situations in terms of human resources allocation, which might be only for one activity, reaching more than 10 modes. As a result, compared to MRCPSP, this issue has a much higher complexity. The Resource Investment Problem (RIP) is a variant of RCPSP where renewable resource constraints are considered decision variables. In many projects, managers, in addition to making decisions about the time of implementation of activities, should determine the number of resources allocated to activities in each period of the implementation of activities according to the status of the project, which means ignoring the constant pattern of resource consumption for activities during their implementation.                           Practical implications: By comparing the algorithms with the indicators of maximum extension, distance from the ideal solution, distance, and several Pareto solutions, it was found that the multi-objective genetic algorithm performs far better than the multi-objective Cuckoo algorithm regarding the criteria, distance from the ideal solution, and the largest expansion. However, in terms of the number of Pareto solutions, the algorithm is not superior to the other algorithms. Therefore, it can be concluded that the multi-objective genetic algorithm has relatively a better performance than the multi-objective Cuckoo algorithm.            Social implications: In this research, each activity can be performed with several different situations in terms of human resource allocation, which may reach more than 10 situations just for one activity. As a result, compared to MRCPSP, this issue has a higher level of complexity. Literature review indicates that being multi-skilled increases the productivity, quality, and consistency of work and gives managers more flexibility in work allocation.               Originality/value: One of the most important branches of project scheduling knowledge is the problem of project scheduling with limited resources. This new concept has led to the development of one of the most general modes of scheduling problems under the title of multi-mode project scheduling with limited resources, which solves many real problems and can be modeled for application.</abstract><pub>University of Isfahan</pub><doi>10.22108/pom.2023.135716.1478</doi><oa>free_for_read</oa></addata></record>
fulltext fulltext
identifier EISSN: 2423-6950
ispartof Mudīrīyyat-i tawlīd va ʻamalīyyāt, 2023-03, Vol.14 (1), p.1-20
issn 2423-6950
language per
recordid cdi_doaj_primary_oai_doaj_org_article_4e7b1ae3b16a4f08a3ffa1ed9a187260
source DOAJ Directory of Open Access Journals
subjects meta-heuristic algorithms
multiskilled manpower
parameter setting
project scheduling
title Fuzzy multi-objective modeling of project scheduling with multi-skill resource constraints with the ability to change the level of skills and interrupt activities
url http://sfxeu10.hosted.exlibrisgroup.com/loughborough?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-12T23%3A57%3A37IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-doaj&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Fuzzy%20multi-objective%20modeling%20of%20project%20scheduling%20with%20multi-skill%20resource%20constraints%20with%20the%20ability%20to%20change%20the%20level%20of%20skills%20and%20interrupt%20activities&rft.jtitle=Mudi%CC%84ri%CC%84yyat-i%20tawli%CC%84d%20va%20%CA%BBamali%CC%84yya%CC%84t&rft.au=Mojtaba%20Salehi&rft.date=2023-03-01&rft.volume=14&rft.issue=1&rft.spage=1&rft.epage=20&rft.pages=1-20&rft.eissn=2423-6950&rft_id=info:doi/10.22108/pom.2023.135716.1478&rft_dat=%3Cdoaj%3Eoai_doaj_org_article_4e7b1ae3b16a4f08a3ffa1ed9a187260%3C/doaj%3E%3Cgrp_id%3Ecdi_FETCH-doaj_primary_oai_doaj_org_article_4e7b1ae3b16a4f08a3ffa1ed9a1872603%3C/grp_id%3E%3Coa%3E%3C/oa%3E%3Curl%3E%3C/url%3E&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true