Order Releasing and Scheduling for a Multi-Item MTO Industry: An Efficient Heuristic Based on Drum Buffer Rope
Increasing productivity and efficiency in factories with make-to-order (MTO) production systems have attracted growing interest of academia and industry. In MTO companies, efficient order release and schedule are essential for succeeding in today’s marketplace. However, dynamic demand of customers a...
Saved in:
Published in: | Applied sciences 2022-02, Vol.12 (4), p.1925 |
---|---|
Main Authors: | , , , , |
Format: | Article |
Language: | English |
Subjects: | |
Citations: | Items that this one cites Items that cite this one |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
cited_by | cdi_FETCH-LOGICAL-c364t-e639d22cdf868d8624b56d870002c7a7c2f8521959ea4bf8e6a5b1e890aa08953 |
---|---|
cites | cdi_FETCH-LOGICAL-c364t-e639d22cdf868d8624b56d870002c7a7c2f8521959ea4bf8e6a5b1e890aa08953 |
container_end_page | |
container_issue | 4 |
container_start_page | 1925 |
container_title | Applied sciences |
container_volume | 12 |
creator | Yue, Lei Xu, Guangyan Mumtaz, Jabir Chen, Yarong Zou, Tao |
description | Increasing productivity and efficiency in factories with make-to-order (MTO) production systems have attracted growing interest of academia and industry. In MTO companies, efficient order release and schedule are essential for succeeding in today’s marketplace. However, dynamic demand of customers and constrained resources make it difficult to achieve, as well as limiting the profits. Thus, to overcome the problem of order releasing and multi-item scheduling considering the capacity constrained resources investigated, a heuristic approach is proposed based on the drum-buffer-rope (DBR) method. The proposed heuristic is tested on different types of problems based on due date tightness and demand of products. The performance of the proposed heuristic is compared with other famous heuristic methods in literature. End results indicate that the proposed heuristic based on the DBR method outperforms against the other competitors, and it gives more significant results when optimal buffer size is adopted. |
doi_str_mv | 10.3390/app12041925 |
format | article |
fullrecord | <record><control><sourceid>proquest_doaj_</sourceid><recordid>TN_cdi_doaj_primary_oai_doaj_org_article_517a1535288e497ba9e91c86efdf3727</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><doaj_id>oai_doaj_org_article_517a1535288e497ba9e91c86efdf3727</doaj_id><sourcerecordid>2632201310</sourcerecordid><originalsourceid>FETCH-LOGICAL-c364t-e639d22cdf868d8624b56d870002c7a7c2f8521959ea4bf8e6a5b1e890aa08953</originalsourceid><addsrcrecordid>eNpNUctqG0EQXEwCEbZP-YEBH8Mm89h55SYpdiywEcT2eWjN9NgrVjubmd2D_z4rywT3pbuaoqqgquoro9-FsPQHDAPjtGGWy7NqwalWtWiY_vTh_lJdlrKn81gmDKOLqt_mgJn8wQ6htP0zgT6QB_-CYeqOMKZMgNxP3djWmxEP5P5xSzZ9mMqYX3-SZU-uY2x9i_1IbnHKbRlbT1ZQMJDUk195OpDVFOPRIw14UX2O0BW8fN_n1dPN9eP6tr7b_t6sl3e1F6oZa1TCBs59iEaZYBRvdlIFo-fg3GvQnkcjObPSIjS7aFCB3DE0lgJQY6U4rzYn3ZBg74bcHiC_ugSte3uk_Owgz0k7dJJpYFJIbgw2Vu_AomXeKIwhCs31rHV10hpy-jthGd0-Tbmf4zuuBOeUCUZn1rcTy-dUSsb435VRd-zHfehH_AOFw4Bf</addsrcrecordid><sourcetype>Open Website</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>2632201310</pqid></control><display><type>article</type><title>Order Releasing and Scheduling for a Multi-Item MTO Industry: An Efficient Heuristic Based on Drum Buffer Rope</title><source>Publicly Available Content Database</source><creator>Yue, Lei ; Xu, Guangyan ; Mumtaz, Jabir ; Chen, Yarong ; Zou, Tao</creator><creatorcontrib>Yue, Lei ; Xu, Guangyan ; Mumtaz, Jabir ; Chen, Yarong ; Zou, Tao</creatorcontrib><description>Increasing productivity and efficiency in factories with make-to-order (MTO) production systems have attracted growing interest of academia and industry. In MTO companies, efficient order release and schedule are essential for succeeding in today’s marketplace. However, dynamic demand of customers and constrained resources make it difficult to achieve, as well as limiting the profits. Thus, to overcome the problem of order releasing and multi-item scheduling considering the capacity constrained resources investigated, a heuristic approach is proposed based on the drum-buffer-rope (DBR) method. The proposed heuristic is tested on different types of problems based on due date tightness and demand of products. The performance of the proposed heuristic is compared with other famous heuristic methods in literature. End results indicate that the proposed heuristic based on the DBR method outperforms against the other competitors, and it gives more significant results when optimal buffer size is adopted.</description><identifier>ISSN: 2076-3417</identifier><identifier>EISSN: 2076-3417</identifier><identifier>DOI: 10.3390/app12041925</identifier><language>eng</language><publisher>Basel: MDPI AG</publisher><subject>Assembly lines ; capacity constrained resource ; Consumption ; drum buffer rope ; Heuristic ; heuristic algorithm ; Inventory ; Manufacturing ; multi-item scheduling ; order releasing ; Problem solving ; Production planning ; Scheduling ; Tightness ; Work in process</subject><ispartof>Applied sciences, 2022-02, Vol.12 (4), p.1925</ispartof><rights>2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/). Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License.</rights><lds50>peer_reviewed</lds50><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed><citedby>FETCH-LOGICAL-c364t-e639d22cdf868d8624b56d870002c7a7c2f8521959ea4bf8e6a5b1e890aa08953</citedby><cites>FETCH-LOGICAL-c364t-e639d22cdf868d8624b56d870002c7a7c2f8521959ea4bf8e6a5b1e890aa08953</cites><orcidid>0000-0002-6386-272X</orcidid></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktopdf>$$Uhttps://www.proquest.com/docview/2632201310/fulltextPDF?pq-origsite=primo$$EPDF$$P50$$Gproquest$$Hfree_for_read</linktopdf><linktohtml>$$Uhttps://www.proquest.com/docview/2632201310?pq-origsite=primo$$EHTML$$P50$$Gproquest$$Hfree_for_read</linktohtml><link.rule.ids>314,776,780,25732,27903,27904,36991,44569,74872</link.rule.ids></links><search><creatorcontrib>Yue, Lei</creatorcontrib><creatorcontrib>Xu, Guangyan</creatorcontrib><creatorcontrib>Mumtaz, Jabir</creatorcontrib><creatorcontrib>Chen, Yarong</creatorcontrib><creatorcontrib>Zou, Tao</creatorcontrib><title>Order Releasing and Scheduling for a Multi-Item MTO Industry: An Efficient Heuristic Based on Drum Buffer Rope</title><title>Applied sciences</title><description>Increasing productivity and efficiency in factories with make-to-order (MTO) production systems have attracted growing interest of academia and industry. In MTO companies, efficient order release and schedule are essential for succeeding in today’s marketplace. However, dynamic demand of customers and constrained resources make it difficult to achieve, as well as limiting the profits. Thus, to overcome the problem of order releasing and multi-item scheduling considering the capacity constrained resources investigated, a heuristic approach is proposed based on the drum-buffer-rope (DBR) method. The proposed heuristic is tested on different types of problems based on due date tightness and demand of products. The performance of the proposed heuristic is compared with other famous heuristic methods in literature. End results indicate that the proposed heuristic based on the DBR method outperforms against the other competitors, and it gives more significant results when optimal buffer size is adopted.</description><subject>Assembly lines</subject><subject>capacity constrained resource</subject><subject>Consumption</subject><subject>drum buffer rope</subject><subject>Heuristic</subject><subject>heuristic algorithm</subject><subject>Inventory</subject><subject>Manufacturing</subject><subject>multi-item scheduling</subject><subject>order releasing</subject><subject>Problem solving</subject><subject>Production planning</subject><subject>Scheduling</subject><subject>Tightness</subject><subject>Work in process</subject><issn>2076-3417</issn><issn>2076-3417</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2022</creationdate><recordtype>article</recordtype><sourceid>PIMPY</sourceid><sourceid>DOA</sourceid><recordid>eNpNUctqG0EQXEwCEbZP-YEBH8Mm89h55SYpdiywEcT2eWjN9NgrVjubmd2D_z4rywT3pbuaoqqgquoro9-FsPQHDAPjtGGWy7NqwalWtWiY_vTh_lJdlrKn81gmDKOLqt_mgJn8wQ6htP0zgT6QB_-CYeqOMKZMgNxP3djWmxEP5P5xSzZ9mMqYX3-SZU-uY2x9i_1IbnHKbRlbT1ZQMJDUk195OpDVFOPRIw14UX2O0BW8fN_n1dPN9eP6tr7b_t6sl3e1F6oZa1TCBs59iEaZYBRvdlIFo-fg3GvQnkcjObPSIjS7aFCB3DE0lgJQY6U4rzYn3ZBg74bcHiC_ugSte3uk_Owgz0k7dJJpYFJIbgw2Vu_AomXeKIwhCs31rHV10hpy-jthGd0-Tbmf4zuuBOeUCUZn1rcTy-dUSsb435VRd-zHfehH_AOFw4Bf</recordid><startdate>20220201</startdate><enddate>20220201</enddate><creator>Yue, Lei</creator><creator>Xu, Guangyan</creator><creator>Mumtaz, Jabir</creator><creator>Chen, Yarong</creator><creator>Zou, Tao</creator><general>MDPI AG</general><scope>AAYXX</scope><scope>CITATION</scope><scope>ABUWG</scope><scope>AFKRA</scope><scope>AZQEC</scope><scope>BENPR</scope><scope>CCPQU</scope><scope>DWQXO</scope><scope>PIMPY</scope><scope>PQEST</scope><scope>PQQKQ</scope><scope>PQUKI</scope><scope>PRINS</scope><scope>DOA</scope><orcidid>https://orcid.org/0000-0002-6386-272X</orcidid></search><sort><creationdate>20220201</creationdate><title>Order Releasing and Scheduling for a Multi-Item MTO Industry: An Efficient Heuristic Based on Drum Buffer Rope</title><author>Yue, Lei ; Xu, Guangyan ; Mumtaz, Jabir ; Chen, Yarong ; Zou, Tao</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c364t-e639d22cdf868d8624b56d870002c7a7c2f8521959ea4bf8e6a5b1e890aa08953</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2022</creationdate><topic>Assembly lines</topic><topic>capacity constrained resource</topic><topic>Consumption</topic><topic>drum buffer rope</topic><topic>Heuristic</topic><topic>heuristic algorithm</topic><topic>Inventory</topic><topic>Manufacturing</topic><topic>multi-item scheduling</topic><topic>order releasing</topic><topic>Problem solving</topic><topic>Production planning</topic><topic>Scheduling</topic><topic>Tightness</topic><topic>Work in process</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Yue, Lei</creatorcontrib><creatorcontrib>Xu, Guangyan</creatorcontrib><creatorcontrib>Mumtaz, Jabir</creatorcontrib><creatorcontrib>Chen, Yarong</creatorcontrib><creatorcontrib>Zou, Tao</creatorcontrib><collection>CrossRef</collection><collection>ProQuest Central (Alumni)</collection><collection>ProQuest Central</collection><collection>ProQuest Central Essentials</collection><collection>ProQuest Central</collection><collection>ProQuest One Community College</collection><collection>ProQuest Central Korea</collection><collection>Publicly Available Content Database</collection><collection>ProQuest One Academic Eastern Edition (DO NOT USE)</collection><collection>ProQuest One Academic</collection><collection>ProQuest One Academic UKI Edition</collection><collection>ProQuest Central China</collection><collection>DOAJ Directory of Open Access Journals</collection><jtitle>Applied sciences</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Yue, Lei</au><au>Xu, Guangyan</au><au>Mumtaz, Jabir</au><au>Chen, Yarong</au><au>Zou, Tao</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Order Releasing and Scheduling for a Multi-Item MTO Industry: An Efficient Heuristic Based on Drum Buffer Rope</atitle><jtitle>Applied sciences</jtitle><date>2022-02-01</date><risdate>2022</risdate><volume>12</volume><issue>4</issue><spage>1925</spage><pages>1925-</pages><issn>2076-3417</issn><eissn>2076-3417</eissn><abstract>Increasing productivity and efficiency in factories with make-to-order (MTO) production systems have attracted growing interest of academia and industry. In MTO companies, efficient order release and schedule are essential for succeeding in today’s marketplace. However, dynamic demand of customers and constrained resources make it difficult to achieve, as well as limiting the profits. Thus, to overcome the problem of order releasing and multi-item scheduling considering the capacity constrained resources investigated, a heuristic approach is proposed based on the drum-buffer-rope (DBR) method. The proposed heuristic is tested on different types of problems based on due date tightness and demand of products. The performance of the proposed heuristic is compared with other famous heuristic methods in literature. End results indicate that the proposed heuristic based on the DBR method outperforms against the other competitors, and it gives more significant results when optimal buffer size is adopted.</abstract><cop>Basel</cop><pub>MDPI AG</pub><doi>10.3390/app12041925</doi><orcidid>https://orcid.org/0000-0002-6386-272X</orcidid><oa>free_for_read</oa></addata></record> |
fulltext | fulltext |
identifier | ISSN: 2076-3417 |
ispartof | Applied sciences, 2022-02, Vol.12 (4), p.1925 |
issn | 2076-3417 2076-3417 |
language | eng |
recordid | cdi_doaj_primary_oai_doaj_org_article_517a1535288e497ba9e91c86efdf3727 |
source | Publicly Available Content Database |
subjects | Assembly lines capacity constrained resource Consumption drum buffer rope Heuristic heuristic algorithm Inventory Manufacturing multi-item scheduling order releasing Problem solving Production planning Scheduling Tightness Work in process |
title | Order Releasing and Scheduling for a Multi-Item MTO Industry: An Efficient Heuristic Based on Drum Buffer Rope |
url | http://sfxeu10.hosted.exlibrisgroup.com/loughborough?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-23T21%3A50%3A13IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_doaj_&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Order%20Releasing%20and%20Scheduling%20for%20a%20Multi-Item%20MTO%20Industry:%20An%20Efficient%20Heuristic%20Based%20on%20Drum%20Buffer%20Rope&rft.jtitle=Applied%20sciences&rft.au=Yue,%20Lei&rft.date=2022-02-01&rft.volume=12&rft.issue=4&rft.spage=1925&rft.pages=1925-&rft.issn=2076-3417&rft.eissn=2076-3417&rft_id=info:doi/10.3390/app12041925&rft_dat=%3Cproquest_doaj_%3E2632201310%3C/proquest_doaj_%3E%3Cgrp_id%3Ecdi_FETCH-LOGICAL-c364t-e639d22cdf868d8624b56d870002c7a7c2f8521959ea4bf8e6a5b1e890aa08953%3C/grp_id%3E%3Coa%3E%3C/oa%3E%3Curl%3E%3C/url%3E&rft_id=info:oai/&rft_pqid=2632201310&rft_id=info:pmid/&rfr_iscdi=true |