Hybrid approach for cost estimation of sustainable building projects using artificial neural networks

Inaccurate estimation in sustainable construction projects is a significant challenge for appraisers, particularly when data and knowledge about the projects are lacking. As a result, there is a need to use cutting-edge technology to solve the issue of estimation inaccuracy. Iraq’s productivity esti...

Full description

Saved in:
Bibliographic Details
Published in:Open Engineering (Warsaw) 2024-03, Vol.14 (1), p.1-14
Main Authors: Al-Somaydaii, Jumaa A., Albadri, Aminah T., Al-Zwainy, Faiq M. S.
Format: Article
Language:English
Subjects:
Citations: Items that this one cites
Online Access:Get full text
Tags: Add Tag
No Tags, Be the first to tag this record!
cited_by
cites cdi_FETCH-LOGICAL-c347t-bdb1c280d495cc944496cf8642b2d81a7ac9938dbf7ac091256dae9ef22216603
container_end_page 14
container_issue 1
container_start_page 1
container_title Open Engineering (Warsaw)
container_volume 14
creator Al-Somaydaii, Jumaa A.
Albadri, Aminah T.
Al-Zwainy, Faiq M. S.
description Inaccurate estimation in sustainable construction projects is a significant challenge for appraisers, particularly when data and knowledge about the projects are lacking. As a result, there is a need to use cutting-edge technology to solve the issue of estimation inaccuracy. Iraq’s productivity estimates are now made using outdated, ineffective methodologies and procedures. In addition, it is essential to implement cutting-edge, quick, precise, and adaptable technology for productivity estimation. This study’s major goal is to calculate the overall costs of sustainable buildings using the cutting-edge technique known as artificial neural networks (ANNs). For Iraq’s construction industry to handle projects successfully, ANNs must be used as a new technology, a methodology developed to estimate the overall costs of sustainable construction projects. In this study, the process of cost estimation was modeled using ANNs. Investigations of a number of examples involving the creation of ANNs have also been made, including network design and internal elements and how much they impact the effectiveness of models built using ANNs. Equations were developed to determine structural productivity. These networks were shown to have extremely strong predictive power for both accounting coefficients ( ) (93.33%) and the overall costs of sustainable construction projects, with a prediction accuracy of 87.00 and 93.33%, respectively.
doi_str_mv 10.1515/eng-2022-0485
format article
fullrecord <record><control><sourceid>walterdegruyter_doaj_</sourceid><recordid>TN_cdi_doaj_primary_oai_doaj_org_article_9763f4c8b4da42c0b1c298db3bb4eb1e</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><doaj_id>oai_doaj_org_article_9763f4c8b4da42c0b1c298db3bb4eb1e</doaj_id><sourcerecordid>10_1515_eng_2022_0485141</sourcerecordid><originalsourceid>FETCH-LOGICAL-c347t-bdb1c280d495cc944496cf8642b2d81a7ac9938dbf7ac091256dae9ef22216603</originalsourceid><addsrcrecordid>eNptkE1LAzEQhoMoWGqP3vMHVvO1HzlKUSsUvOg55HNNXTclyVL67822Ih48zTvDzDMzLwC3GN3hGtf3duwrggipEOvqC7AglOOqZpRf_tHXYJXSDiGEa9ryFi-A3RxV9AbK_T4GqT-gCxHqkDK0KfsvmX0YYXAwTSlLP0o1WKgmPxg_9rCM7KzOCU5pTmXM3nnt5QBHO8VTyIcQP9MNuHJySHb1E5fg_enxbb2ptq_PL-uHbaUpa3OljMKadMgwXmvNGWO80a5rGFHEdFi2UnNOO6NcUYhjUjdGWm4dIQQ3DaJL8HLmmiB3Yh_LA_EogvTiVAixF_ORerCCtw11THeKGcmIRvNmXtBUKWYVtoVVnVk6hpSidb88jMRsuSiWi9lyMVte-rtz_0EO2UZj-zgdixC7MMWxfP3_HGaYfgOJGomH</addsrcrecordid><sourcetype>Open Website</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype></control><display><type>article</type><title>Hybrid approach for cost estimation of sustainable building projects using artificial neural networks</title><source>De Gruyter Open Access Journals</source><creator>Al-Somaydaii, Jumaa A. ; Albadri, Aminah T. ; Al-Zwainy, Faiq M. S.</creator><creatorcontrib>Al-Somaydaii, Jumaa A. ; Albadri, Aminah T. ; Al-Zwainy, Faiq M. S.</creatorcontrib><description>Inaccurate estimation in sustainable construction projects is a significant challenge for appraisers, particularly when data and knowledge about the projects are lacking. As a result, there is a need to use cutting-edge technology to solve the issue of estimation inaccuracy. Iraq’s productivity estimates are now made using outdated, ineffective methodologies and procedures. In addition, it is essential to implement cutting-edge, quick, precise, and adaptable technology for productivity estimation. This study’s major goal is to calculate the overall costs of sustainable buildings using the cutting-edge technique known as artificial neural networks (ANNs). For Iraq’s construction industry to handle projects successfully, ANNs must be used as a new technology, a methodology developed to estimate the overall costs of sustainable construction projects. In this study, the process of cost estimation was modeled using ANNs. Investigations of a number of examples involving the creation of ANNs have also been made, including network design and internal elements and how much they impact the effectiveness of models built using ANNs. Equations were developed to determine structural productivity. These networks were shown to have extremely strong predictive power for both accounting coefficients ( ) (93.33%) and the overall costs of sustainable construction projects, with a prediction accuracy of 87.00 and 93.33%, respectively.</description><identifier>ISSN: 2391-5439</identifier><identifier>EISSN: 2391-5439</identifier><identifier>DOI: 10.1515/eng-2022-0485</identifier><language>eng</language><publisher>De Gruyter</publisher><subject>correlation coefficient ; cost estimation ; neural network ; sustainable buildings</subject><ispartof>Open Engineering (Warsaw), 2024-03, Vol.14 (1), p.1-14</ispartof><lds50>peer_reviewed</lds50><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed><cites>FETCH-LOGICAL-c347t-bdb1c280d495cc944496cf8642b2d81a7ac9938dbf7ac091256dae9ef22216603</cites></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktopdf>$$Uhttps://www.degruyter.com/document/doi/10.1515/eng-2022-0485/pdf$$EPDF$$P50$$Gwalterdegruyter$$Hfree_for_read</linktopdf><linktohtml>$$Uhttps://www.degruyter.com/document/doi/10.1515/eng-2022-0485/html$$EHTML$$P50$$Gwalterdegruyter$$Hfree_for_read</linktohtml><link.rule.ids>314,776,780,27903,27904,66905,68689</link.rule.ids></links><search><creatorcontrib>Al-Somaydaii, Jumaa A.</creatorcontrib><creatorcontrib>Albadri, Aminah T.</creatorcontrib><creatorcontrib>Al-Zwainy, Faiq M. S.</creatorcontrib><title>Hybrid approach for cost estimation of sustainable building projects using artificial neural networks</title><title>Open Engineering (Warsaw)</title><description>Inaccurate estimation in sustainable construction projects is a significant challenge for appraisers, particularly when data and knowledge about the projects are lacking. As a result, there is a need to use cutting-edge technology to solve the issue of estimation inaccuracy. Iraq’s productivity estimates are now made using outdated, ineffective methodologies and procedures. In addition, it is essential to implement cutting-edge, quick, precise, and adaptable technology for productivity estimation. This study’s major goal is to calculate the overall costs of sustainable buildings using the cutting-edge technique known as artificial neural networks (ANNs). For Iraq’s construction industry to handle projects successfully, ANNs must be used as a new technology, a methodology developed to estimate the overall costs of sustainable construction projects. In this study, the process of cost estimation was modeled using ANNs. Investigations of a number of examples involving the creation of ANNs have also been made, including network design and internal elements and how much they impact the effectiveness of models built using ANNs. Equations were developed to determine structural productivity. These networks were shown to have extremely strong predictive power for both accounting coefficients ( ) (93.33%) and the overall costs of sustainable construction projects, with a prediction accuracy of 87.00 and 93.33%, respectively.</description><subject>correlation coefficient</subject><subject>cost estimation</subject><subject>neural network</subject><subject>sustainable buildings</subject><issn>2391-5439</issn><issn>2391-5439</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2024</creationdate><recordtype>article</recordtype><sourceid>DOA</sourceid><recordid>eNptkE1LAzEQhoMoWGqP3vMHVvO1HzlKUSsUvOg55HNNXTclyVL67822Ih48zTvDzDMzLwC3GN3hGtf3duwrggipEOvqC7AglOOqZpRf_tHXYJXSDiGEa9ryFi-A3RxV9AbK_T4GqT-gCxHqkDK0KfsvmX0YYXAwTSlLP0o1WKgmPxg_9rCM7KzOCU5pTmXM3nnt5QBHO8VTyIcQP9MNuHJySHb1E5fg_enxbb2ptq_PL-uHbaUpa3OljMKadMgwXmvNGWO80a5rGFHEdFi2UnNOO6NcUYhjUjdGWm4dIQQ3DaJL8HLmmiB3Yh_LA_EogvTiVAixF_ORerCCtw11THeKGcmIRvNmXtBUKWYVtoVVnVk6hpSidb88jMRsuSiWi9lyMVte-rtz_0EO2UZj-zgdixC7MMWxfP3_HGaYfgOJGomH</recordid><startdate>20240320</startdate><enddate>20240320</enddate><creator>Al-Somaydaii, Jumaa A.</creator><creator>Albadri, Aminah T.</creator><creator>Al-Zwainy, Faiq M. S.</creator><general>De Gruyter</general><scope>AAYXX</scope><scope>CITATION</scope><scope>DOA</scope></search><sort><creationdate>20240320</creationdate><title>Hybrid approach for cost estimation of sustainable building projects using artificial neural networks</title><author>Al-Somaydaii, Jumaa A. ; Albadri, Aminah T. ; Al-Zwainy, Faiq M. S.</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c347t-bdb1c280d495cc944496cf8642b2d81a7ac9938dbf7ac091256dae9ef22216603</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2024</creationdate><topic>correlation coefficient</topic><topic>cost estimation</topic><topic>neural network</topic><topic>sustainable buildings</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Al-Somaydaii, Jumaa A.</creatorcontrib><creatorcontrib>Albadri, Aminah T.</creatorcontrib><creatorcontrib>Al-Zwainy, Faiq M. S.</creatorcontrib><collection>CrossRef</collection><collection>Open Access: DOAJ - Directory of Open Access Journals</collection><jtitle>Open Engineering (Warsaw)</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Al-Somaydaii, Jumaa A.</au><au>Albadri, Aminah T.</au><au>Al-Zwainy, Faiq M. S.</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Hybrid approach for cost estimation of sustainable building projects using artificial neural networks</atitle><jtitle>Open Engineering (Warsaw)</jtitle><date>2024-03-20</date><risdate>2024</risdate><volume>14</volume><issue>1</issue><spage>1</spage><epage>14</epage><pages>1-14</pages><issn>2391-5439</issn><eissn>2391-5439</eissn><abstract>Inaccurate estimation in sustainable construction projects is a significant challenge for appraisers, particularly when data and knowledge about the projects are lacking. As a result, there is a need to use cutting-edge technology to solve the issue of estimation inaccuracy. Iraq’s productivity estimates are now made using outdated, ineffective methodologies and procedures. In addition, it is essential to implement cutting-edge, quick, precise, and adaptable technology for productivity estimation. This study’s major goal is to calculate the overall costs of sustainable buildings using the cutting-edge technique known as artificial neural networks (ANNs). For Iraq’s construction industry to handle projects successfully, ANNs must be used as a new technology, a methodology developed to estimate the overall costs of sustainable construction projects. In this study, the process of cost estimation was modeled using ANNs. Investigations of a number of examples involving the creation of ANNs have also been made, including network design and internal elements and how much they impact the effectiveness of models built using ANNs. Equations were developed to determine structural productivity. These networks were shown to have extremely strong predictive power for both accounting coefficients ( ) (93.33%) and the overall costs of sustainable construction projects, with a prediction accuracy of 87.00 and 93.33%, respectively.</abstract><pub>De Gruyter</pub><doi>10.1515/eng-2022-0485</doi><tpages>8</tpages><oa>free_for_read</oa></addata></record>
fulltext fulltext
identifier ISSN: 2391-5439
ispartof Open Engineering (Warsaw), 2024-03, Vol.14 (1), p.1-14
issn 2391-5439
2391-5439
language eng
recordid cdi_doaj_primary_oai_doaj_org_article_9763f4c8b4da42c0b1c298db3bb4eb1e
source De Gruyter Open Access Journals
subjects correlation coefficient
cost estimation
neural network
sustainable buildings
title Hybrid approach for cost estimation of sustainable building projects using artificial neural networks
url http://sfxeu10.hosted.exlibrisgroup.com/loughborough?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-21T16%3A44%3A49IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-walterdegruyter_doaj_&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Hybrid%20approach%20for%20cost%20estimation%20of%20sustainable%20building%20projects%20using%20artificial%20neural%20networks&rft.jtitle=Open%20Engineering%20(Warsaw)&rft.au=Al-Somaydaii,%20Jumaa%20A.&rft.date=2024-03-20&rft.volume=14&rft.issue=1&rft.spage=1&rft.epage=14&rft.pages=1-14&rft.issn=2391-5439&rft.eissn=2391-5439&rft_id=info:doi/10.1515/eng-2022-0485&rft_dat=%3Cwalterdegruyter_doaj_%3E10_1515_eng_2022_0485141%3C/walterdegruyter_doaj_%3E%3Cgrp_id%3Ecdi_FETCH-LOGICAL-c347t-bdb1c280d495cc944496cf8642b2d81a7ac9938dbf7ac091256dae9ef22216603%3C/grp_id%3E%3Coa%3E%3C/oa%3E%3Curl%3E%3C/url%3E&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true