An Integrated Model for Multi-Mode Resource-Constrained Multi-Project Scheduling Problems Considering Supply Management with Sustainable Approach in the Construction Industry under Uncertainty Using Evidence Theory and Optimization Algorithms

In this study, the multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs) considering supply management and sustainable approach in the construction industry under uncertain conditions have been investigated using evidence theory to mathematical modeling and solving by multi-o...

Full description

Saved in:
Bibliographic Details
Published in:Buildings (Basel) 2023-08, Vol.13 (8), p.2023
Main Authors: Ghoroqi, Mahyar, Ghoddousi, Parviz, Makui, Ahmad, Shirzadi Javid, Ali Akbar, Talebi, Saeed
Format: Article
Language:English
Subjects:
Citations: Items that this one cites
Items that cite this one
Online Access:Get full text
Tags: Add Tag
No Tags, Be the first to tag this record!
cited_by cdi_FETCH-LOGICAL-c421t-7ad137f7868dde4049daaff75457c6e5f4110bfc54a0859fe2701e49f6fe862d3
cites cdi_FETCH-LOGICAL-c421t-7ad137f7868dde4049daaff75457c6e5f4110bfc54a0859fe2701e49f6fe862d3
container_end_page
container_issue 8
container_start_page 2023
container_title Buildings (Basel)
container_volume 13
creator Ghoroqi, Mahyar
Ghoddousi, Parviz
Makui, Ahmad
Shirzadi Javid, Ali Akbar
Talebi, Saeed
description In this study, the multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs) considering supply management and sustainable approach in the construction industry under uncertain conditions have been investigated using evidence theory to mathematical modeling and solving by multi-objective optimization algorithms. In this regard, a multi-objective mathematical model has been proposed, in which the first objective function aims to maximize a weighted selection of projects based on economic, environmental, technical, social, organizational, and competitive factors; the second objective function is focused on maximizing profit, and the third objective function is aimed at minimizing the risk of supply management. Moreover, various components, such as interest rates, carbon penalties, and other implementation limitations and additional constraints, have also been considered in the modeling and mathematical relationships to improve the model’s performance and make it more relevant to real-world conditions and related issues, leading to better practical applications. In the mathematical modeling adopted, the processing time of project activities has been considered uncertain, and the evidence theory has been utilized. This method can provide a flexible and rational approach based on evidence and knowledge in the face of uncertainty. In addition, to solve the proposed multi-objective mathematical model, metaheuristic optimization algorithms, such as the differential evolution (DE) algorithm based on the Pareto archive, have been used, and for evaluating the results, the non-dominated sorting genetic algorithm II (NSGA-II) has also been employed. Furthermore, the results have been compared based on multi-objective evaluation criteria, such as quality metric (QM), spacing metric (SM), and diversity metric (DM). It is worth noting that to investigate the performance and application of the proposed model, multiple evaluations have been conducted on sample problems with different dimensions, as well as a case study on residential apartment construction projects by a contracting company. In this respect, the answers obtained from solving the model using the multi-objective DE algorithm were better and superior to the NSGA-II algorithm and had a more favorable performance. Generally, the results indicate that using the integrated multi-objective mathematical model in the present research for managing and scheduling multi-mode resource-constrained multi
doi_str_mv 10.3390/buildings13082023
format article
fullrecord <record><control><sourceid>gale_doaj_</sourceid><recordid>TN_cdi_doaj_primary_oai_doaj_org_article_b27fae37d52344288b22c8a529f9f02c</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><galeid>A762478719</galeid><doaj_id>oai_doaj_org_article_b27fae37d52344288b22c8a529f9f02c</doaj_id><sourcerecordid>A762478719</sourcerecordid><originalsourceid>FETCH-LOGICAL-c421t-7ad137f7868dde4049daaff75457c6e5f4110bfc54a0859fe2701e49f6fe862d3</originalsourceid><addsrcrecordid>eNplUsGO2yAQtapW6mq7H9AbUs_eAsbGPkarbRtpo626m7NFYHCIbEgBt8p-dr-g46SqKhUOwOO9N6OZKYr3jN5WVUc_7mY3GueHxCracsqrV8UVp7Iu64p2r_-5vy1uUjpQXG3NeS2uil8rT9Y-wxBVBkM2wcBIbIhkM4_ZlcubfIMU5qihvAs-5aicX5jn_68xHEBn8qT3YOYRcyAI7UaYElnYzkBcwKf5eBxPZKO8GmACn8lPl_cIp4x2CgVkdTzGoPSeOE_yHsgl2KyzC0uKBqnxRGaPjmTrNcRFmU9km5YA9z8wFKLkeQ8Becob8njMbnIv6uywGocQMeaU3hVvrBoT3Pw5r4vtp_vnuy_lw-Pn9d3qodSCs1xKZVglrWyb1hgQVHRGKWtlLWqpG6itYIzurK6Fwmp2FrikDERnGwttw011XawvviaoQ3-MblLx1Afl-jMQ4tCrmJ0eod9xaRVU0tS8EoK37Y5z3aqad7azlGv0-nDxwhp9nyHl_oAt8Zh-z9u66SSrBEPW7YU1KDR13gbslsZtYHI6eLAO8ZVsuJCtZB0K2EWgY0gpgv2bJqP9Mlr9f6NV_QYyoMpa</addsrcrecordid><sourcetype>Open Website</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>2856971341</pqid></control><display><type>article</type><title>An Integrated Model for Multi-Mode Resource-Constrained Multi-Project Scheduling Problems Considering Supply Management with Sustainable Approach in the Construction Industry under Uncertainty Using Evidence Theory and Optimization Algorithms</title><source>Publicly Available Content (ProQuest)</source><creator>Ghoroqi, Mahyar ; Ghoddousi, Parviz ; Makui, Ahmad ; Shirzadi Javid, Ali Akbar ; Talebi, Saeed</creator><creatorcontrib>Ghoroqi, Mahyar ; Ghoddousi, Parviz ; Makui, Ahmad ; Shirzadi Javid, Ali Akbar ; Talebi, Saeed</creatorcontrib><description>In this study, the multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs) considering supply management and sustainable approach in the construction industry under uncertain conditions have been investigated using evidence theory to mathematical modeling and solving by multi-objective optimization algorithms. In this regard, a multi-objective mathematical model has been proposed, in which the first objective function aims to maximize a weighted selection of projects based on economic, environmental, technical, social, organizational, and competitive factors; the second objective function is focused on maximizing profit, and the third objective function is aimed at minimizing the risk of supply management. Moreover, various components, such as interest rates, carbon penalties, and other implementation limitations and additional constraints, have also been considered in the modeling and mathematical relationships to improve the model’s performance and make it more relevant to real-world conditions and related issues, leading to better practical applications. In the mathematical modeling adopted, the processing time of project activities has been considered uncertain, and the evidence theory has been utilized. This method can provide a flexible and rational approach based on evidence and knowledge in the face of uncertainty. In addition, to solve the proposed multi-objective mathematical model, metaheuristic optimization algorithms, such as the differential evolution (DE) algorithm based on the Pareto archive, have been used, and for evaluating the results, the non-dominated sorting genetic algorithm II (NSGA-II) has also been employed. Furthermore, the results have been compared based on multi-objective evaluation criteria, such as quality metric (QM), spacing metric (SM), and diversity metric (DM). It is worth noting that to investigate the performance and application of the proposed model, multiple evaluations have been conducted on sample problems with different dimensions, as well as a case study on residential apartment construction projects by a contracting company. In this respect, the answers obtained from solving the model using the multi-objective DE algorithm were better and superior to the NSGA-II algorithm and had a more favorable performance. Generally, the results indicate that using the integrated multi-objective mathematical model in the present research for managing and scheduling multi-mode resource-constrained multi-project problems, especially in the construction industry, can lead to an optimal state consistent with the desired objectives and can significantly improve the progress and completion of projects.</description><identifier>ISSN: 2075-5309</identifier><identifier>EISSN: 2075-5309</identifier><identifier>DOI: 10.3390/buildings13082023</identifier><language>eng</language><publisher>Basel: MDPI AG</publisher><subject>Algorithms ; Business competition ; Case studies ; Constraints ; Construction industry ; Costs ; evidence theory ; Evolutionary algorithms ; Evolutionary computation ; Genetic algorithms ; Heuristic methods ; Integrated approach ; Interest rates ; Literature reviews ; Mathematical analysis ; Mathematical models ; Mathematical optimization ; metaheuristic optimization algorithms ; multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs) ; multi-objective mathematical modeling ; Multiple objective analysis ; Objective function ; Optimization algorithms ; Pareto optimization ; Profitability ; Profits ; Project engineering ; Project management ; Renewable resources ; Resource scheduling ; Risk reduction ; Scheduling ; Sorting algorithms ; sustainability ; Sustainable development ; Uncertainty</subject><ispartof>Buildings (Basel), 2023-08, Vol.13 (8), p.2023</ispartof><rights>COPYRIGHT 2023 MDPI AG</rights><rights>2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/). Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License.</rights><lds50>peer_reviewed</lds50><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed><citedby>FETCH-LOGICAL-c421t-7ad137f7868dde4049daaff75457c6e5f4110bfc54a0859fe2701e49f6fe862d3</citedby><cites>FETCH-LOGICAL-c421t-7ad137f7868dde4049daaff75457c6e5f4110bfc54a0859fe2701e49f6fe862d3</cites><orcidid>0000-0002-5493-4891 ; 0000-0001-6249-530X ; 0000-0001-6711-0931 ; 0000-0002-5577-333X ; 0000-0002-6105-5991</orcidid></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktopdf>$$Uhttps://www.proquest.com/docview/2856971341/fulltextPDF?pq-origsite=primo$$EPDF$$P50$$Gproquest$$Hfree_for_read</linktopdf><linktohtml>$$Uhttps://www.proquest.com/docview/2856971341?pq-origsite=primo$$EHTML$$P50$$Gproquest$$Hfree_for_read</linktohtml><link.rule.ids>314,777,781,25734,27905,27906,36993,44571,74875</link.rule.ids></links><search><creatorcontrib>Ghoroqi, Mahyar</creatorcontrib><creatorcontrib>Ghoddousi, Parviz</creatorcontrib><creatorcontrib>Makui, Ahmad</creatorcontrib><creatorcontrib>Shirzadi Javid, Ali Akbar</creatorcontrib><creatorcontrib>Talebi, Saeed</creatorcontrib><title>An Integrated Model for Multi-Mode Resource-Constrained Multi-Project Scheduling Problems Considering Supply Management with Sustainable Approach in the Construction Industry under Uncertainty Using Evidence Theory and Optimization Algorithms</title><title>Buildings (Basel)</title><description>In this study, the multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs) considering supply management and sustainable approach in the construction industry under uncertain conditions have been investigated using evidence theory to mathematical modeling and solving by multi-objective optimization algorithms. In this regard, a multi-objective mathematical model has been proposed, in which the first objective function aims to maximize a weighted selection of projects based on economic, environmental, technical, social, organizational, and competitive factors; the second objective function is focused on maximizing profit, and the third objective function is aimed at minimizing the risk of supply management. Moreover, various components, such as interest rates, carbon penalties, and other implementation limitations and additional constraints, have also been considered in the modeling and mathematical relationships to improve the model’s performance and make it more relevant to real-world conditions and related issues, leading to better practical applications. In the mathematical modeling adopted, the processing time of project activities has been considered uncertain, and the evidence theory has been utilized. This method can provide a flexible and rational approach based on evidence and knowledge in the face of uncertainty. In addition, to solve the proposed multi-objective mathematical model, metaheuristic optimization algorithms, such as the differential evolution (DE) algorithm based on the Pareto archive, have been used, and for evaluating the results, the non-dominated sorting genetic algorithm II (NSGA-II) has also been employed. Furthermore, the results have been compared based on multi-objective evaluation criteria, such as quality metric (QM), spacing metric (SM), and diversity metric (DM). It is worth noting that to investigate the performance and application of the proposed model, multiple evaluations have been conducted on sample problems with different dimensions, as well as a case study on residential apartment construction projects by a contracting company. In this respect, the answers obtained from solving the model using the multi-objective DE algorithm were better and superior to the NSGA-II algorithm and had a more favorable performance. Generally, the results indicate that using the integrated multi-objective mathematical model in the present research for managing and scheduling multi-mode resource-constrained multi-project problems, especially in the construction industry, can lead to an optimal state consistent with the desired objectives and can significantly improve the progress and completion of projects.</description><subject>Algorithms</subject><subject>Business competition</subject><subject>Case studies</subject><subject>Constraints</subject><subject>Construction industry</subject><subject>Costs</subject><subject>evidence theory</subject><subject>Evolutionary algorithms</subject><subject>Evolutionary computation</subject><subject>Genetic algorithms</subject><subject>Heuristic methods</subject><subject>Integrated approach</subject><subject>Interest rates</subject><subject>Literature reviews</subject><subject>Mathematical analysis</subject><subject>Mathematical models</subject><subject>Mathematical optimization</subject><subject>metaheuristic optimization algorithms</subject><subject>multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs)</subject><subject>multi-objective mathematical modeling</subject><subject>Multiple objective analysis</subject><subject>Objective function</subject><subject>Optimization algorithms</subject><subject>Pareto optimization</subject><subject>Profitability</subject><subject>Profits</subject><subject>Project engineering</subject><subject>Project management</subject><subject>Renewable resources</subject><subject>Resource scheduling</subject><subject>Risk reduction</subject><subject>Scheduling</subject><subject>Sorting algorithms</subject><subject>sustainability</subject><subject>Sustainable development</subject><subject>Uncertainty</subject><issn>2075-5309</issn><issn>2075-5309</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2023</creationdate><recordtype>article</recordtype><sourceid>PIMPY</sourceid><sourceid>DOA</sourceid><recordid>eNplUsGO2yAQtapW6mq7H9AbUs_eAsbGPkarbRtpo626m7NFYHCIbEgBt8p-dr-g46SqKhUOwOO9N6OZKYr3jN5WVUc_7mY3GueHxCracsqrV8UVp7Iu64p2r_-5vy1uUjpQXG3NeS2uil8rT9Y-wxBVBkM2wcBIbIhkM4_ZlcubfIMU5qihvAs-5aicX5jn_68xHEBn8qT3YOYRcyAI7UaYElnYzkBcwKf5eBxPZKO8GmACn8lPl_cIp4x2CgVkdTzGoPSeOE_yHsgl2KyzC0uKBqnxRGaPjmTrNcRFmU9km5YA9z8wFKLkeQ8Becob8njMbnIv6uywGocQMeaU3hVvrBoT3Pw5r4vtp_vnuy_lw-Pn9d3qodSCs1xKZVglrWyb1hgQVHRGKWtlLWqpG6itYIzurK6Fwmp2FrikDERnGwttw011XawvviaoQ3-MblLx1Afl-jMQ4tCrmJ0eod9xaRVU0tS8EoK37Y5z3aqad7azlGv0-nDxwhp9nyHl_oAt8Zh-z9u66SSrBEPW7YU1KDR13gbslsZtYHI6eLAO8ZVsuJCtZB0K2EWgY0gpgv2bJqP9Mlr9f6NV_QYyoMpa</recordid><startdate>20230801</startdate><enddate>20230801</enddate><creator>Ghoroqi, Mahyar</creator><creator>Ghoddousi, Parviz</creator><creator>Makui, Ahmad</creator><creator>Shirzadi Javid, Ali Akbar</creator><creator>Talebi, Saeed</creator><general>MDPI AG</general><scope>AAYXX</scope><scope>CITATION</scope><scope>8FD</scope><scope>8FE</scope><scope>8FG</scope><scope>ABJCF</scope><scope>ABUWG</scope><scope>AFKRA</scope><scope>ATCPS</scope><scope>AZQEC</scope><scope>BENPR</scope><scope>BGLVJ</scope><scope>BHPHI</scope><scope>CCPQU</scope><scope>DWQXO</scope><scope>FR3</scope><scope>GNUQQ</scope><scope>HCIFZ</scope><scope>KR7</scope><scope>L.-</scope><scope>L6V</scope><scope>M7S</scope><scope>PATMY</scope><scope>PIMPY</scope><scope>PQEST</scope><scope>PQQKQ</scope><scope>PQUKI</scope><scope>PTHSS</scope><scope>PYCSY</scope><scope>DOA</scope><orcidid>https://orcid.org/0000-0002-5493-4891</orcidid><orcidid>https://orcid.org/0000-0001-6249-530X</orcidid><orcidid>https://orcid.org/0000-0001-6711-0931</orcidid><orcidid>https://orcid.org/0000-0002-5577-333X</orcidid><orcidid>https://orcid.org/0000-0002-6105-5991</orcidid></search><sort><creationdate>20230801</creationdate><title>An Integrated Model for Multi-Mode Resource-Constrained Multi-Project Scheduling Problems Considering Supply Management with Sustainable Approach in the Construction Industry under Uncertainty Using Evidence Theory and Optimization Algorithms</title><author>Ghoroqi, Mahyar ; Ghoddousi, Parviz ; Makui, Ahmad ; Shirzadi Javid, Ali Akbar ; Talebi, Saeed</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c421t-7ad137f7868dde4049daaff75457c6e5f4110bfc54a0859fe2701e49f6fe862d3</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2023</creationdate><topic>Algorithms</topic><topic>Business competition</topic><topic>Case studies</topic><topic>Constraints</topic><topic>Construction industry</topic><topic>Costs</topic><topic>evidence theory</topic><topic>Evolutionary algorithms</topic><topic>Evolutionary computation</topic><topic>Genetic algorithms</topic><topic>Heuristic methods</topic><topic>Integrated approach</topic><topic>Interest rates</topic><topic>Literature reviews</topic><topic>Mathematical analysis</topic><topic>Mathematical models</topic><topic>Mathematical optimization</topic><topic>metaheuristic optimization algorithms</topic><topic>multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs)</topic><topic>multi-objective mathematical modeling</topic><topic>Multiple objective analysis</topic><topic>Objective function</topic><topic>Optimization algorithms</topic><topic>Pareto optimization</topic><topic>Profitability</topic><topic>Profits</topic><topic>Project engineering</topic><topic>Project management</topic><topic>Renewable resources</topic><topic>Resource scheduling</topic><topic>Risk reduction</topic><topic>Scheduling</topic><topic>Sorting algorithms</topic><topic>sustainability</topic><topic>Sustainable development</topic><topic>Uncertainty</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Ghoroqi, Mahyar</creatorcontrib><creatorcontrib>Ghoddousi, Parviz</creatorcontrib><creatorcontrib>Makui, Ahmad</creatorcontrib><creatorcontrib>Shirzadi Javid, Ali Akbar</creatorcontrib><creatorcontrib>Talebi, Saeed</creatorcontrib><collection>CrossRef</collection><collection>Technology Research Database</collection><collection>ProQuest SciTech Collection</collection><collection>ProQuest Technology Collection</collection><collection>Materials Science &amp; Engineering Collection</collection><collection>ProQuest Central (Alumni)</collection><collection>ProQuest Central</collection><collection>Agricultural &amp; Environmental Science Collection</collection><collection>ProQuest Central Essentials</collection><collection>ProQuest Central</collection><collection>Technology Collection</collection><collection>ProQuest Natural Science Collection</collection><collection>ProQuest One Community College</collection><collection>ProQuest Central Korea</collection><collection>Engineering Research Database</collection><collection>ProQuest Central Student</collection><collection>SciTech Premium Collection</collection><collection>Civil Engineering Abstracts</collection><collection>ABI/INFORM Professional Advanced</collection><collection>ProQuest Engineering Collection</collection><collection>Engineering Database</collection><collection>Environmental Science Database</collection><collection>Publicly Available Content (ProQuest)</collection><collection>ProQuest One Academic Eastern Edition (DO NOT USE)</collection><collection>ProQuest One Academic</collection><collection>ProQuest One Academic UKI Edition</collection><collection>Engineering Collection</collection><collection>Environmental Science Collection</collection><collection>DOAJ Directory of Open Access Journals</collection><jtitle>Buildings (Basel)</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Ghoroqi, Mahyar</au><au>Ghoddousi, Parviz</au><au>Makui, Ahmad</au><au>Shirzadi Javid, Ali Akbar</au><au>Talebi, Saeed</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>An Integrated Model for Multi-Mode Resource-Constrained Multi-Project Scheduling Problems Considering Supply Management with Sustainable Approach in the Construction Industry under Uncertainty Using Evidence Theory and Optimization Algorithms</atitle><jtitle>Buildings (Basel)</jtitle><date>2023-08-01</date><risdate>2023</risdate><volume>13</volume><issue>8</issue><spage>2023</spage><pages>2023-</pages><issn>2075-5309</issn><eissn>2075-5309</eissn><abstract>In this study, the multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs) considering supply management and sustainable approach in the construction industry under uncertain conditions have been investigated using evidence theory to mathematical modeling and solving by multi-objective optimization algorithms. In this regard, a multi-objective mathematical model has been proposed, in which the first objective function aims to maximize a weighted selection of projects based on economic, environmental, technical, social, organizational, and competitive factors; the second objective function is focused on maximizing profit, and the third objective function is aimed at minimizing the risk of supply management. Moreover, various components, such as interest rates, carbon penalties, and other implementation limitations and additional constraints, have also been considered in the modeling and mathematical relationships to improve the model’s performance and make it more relevant to real-world conditions and related issues, leading to better practical applications. In the mathematical modeling adopted, the processing time of project activities has been considered uncertain, and the evidence theory has been utilized. This method can provide a flexible and rational approach based on evidence and knowledge in the face of uncertainty. In addition, to solve the proposed multi-objective mathematical model, metaheuristic optimization algorithms, such as the differential evolution (DE) algorithm based on the Pareto archive, have been used, and for evaluating the results, the non-dominated sorting genetic algorithm II (NSGA-II) has also been employed. Furthermore, the results have been compared based on multi-objective evaluation criteria, such as quality metric (QM), spacing metric (SM), and diversity metric (DM). It is worth noting that to investigate the performance and application of the proposed model, multiple evaluations have been conducted on sample problems with different dimensions, as well as a case study on residential apartment construction projects by a contracting company. In this respect, the answers obtained from solving the model using the multi-objective DE algorithm were better and superior to the NSGA-II algorithm and had a more favorable performance. Generally, the results indicate that using the integrated multi-objective mathematical model in the present research for managing and scheduling multi-mode resource-constrained multi-project problems, especially in the construction industry, can lead to an optimal state consistent with the desired objectives and can significantly improve the progress and completion of projects.</abstract><cop>Basel</cop><pub>MDPI AG</pub><doi>10.3390/buildings13082023</doi><orcidid>https://orcid.org/0000-0002-5493-4891</orcidid><orcidid>https://orcid.org/0000-0001-6249-530X</orcidid><orcidid>https://orcid.org/0000-0001-6711-0931</orcidid><orcidid>https://orcid.org/0000-0002-5577-333X</orcidid><orcidid>https://orcid.org/0000-0002-6105-5991</orcidid><oa>free_for_read</oa></addata></record>
fulltext fulltext
identifier ISSN: 2075-5309
ispartof Buildings (Basel), 2023-08, Vol.13 (8), p.2023
issn 2075-5309
2075-5309
language eng
recordid cdi_doaj_primary_oai_doaj_org_article_b27fae37d52344288b22c8a529f9f02c
source Publicly Available Content (ProQuest)
subjects Algorithms
Business competition
Case studies
Constraints
Construction industry
Costs
evidence theory
Evolutionary algorithms
Evolutionary computation
Genetic algorithms
Heuristic methods
Integrated approach
Interest rates
Literature reviews
Mathematical analysis
Mathematical models
Mathematical optimization
metaheuristic optimization algorithms
multi-mode resource-constrained multi-project scheduling problems (MMRCMPSPs)
multi-objective mathematical modeling
Multiple objective analysis
Objective function
Optimization algorithms
Pareto optimization
Profitability
Profits
Project engineering
Project management
Renewable resources
Resource scheduling
Risk reduction
Scheduling
Sorting algorithms
sustainability
Sustainable development
Uncertainty
title An Integrated Model for Multi-Mode Resource-Constrained Multi-Project Scheduling Problems Considering Supply Management with Sustainable Approach in the Construction Industry under Uncertainty Using Evidence Theory and Optimization Algorithms
url http://sfxeu10.hosted.exlibrisgroup.com/loughborough?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-20T02%3A22%3A50IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-gale_doaj_&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=An%20Integrated%20Model%20for%20Multi-Mode%20Resource-Constrained%20Multi-Project%20Scheduling%20Problems%20Considering%20Supply%20Management%20with%20Sustainable%20Approach%20in%20the%20Construction%20Industry%20under%20Uncertainty%20Using%20Evidence%20Theory%20and%20Optimization%20Algorithms&rft.jtitle=Buildings%20(Basel)&rft.au=Ghoroqi,%20Mahyar&rft.date=2023-08-01&rft.volume=13&rft.issue=8&rft.spage=2023&rft.pages=2023-&rft.issn=2075-5309&rft.eissn=2075-5309&rft_id=info:doi/10.3390/buildings13082023&rft_dat=%3Cgale_doaj_%3EA762478719%3C/gale_doaj_%3E%3Cgrp_id%3Ecdi_FETCH-LOGICAL-c421t-7ad137f7868dde4049daaff75457c6e5f4110bfc54a0859fe2701e49f6fe862d3%3C/grp_id%3E%3Coa%3E%3C/oa%3E%3Curl%3E%3C/url%3E&rft_id=info:oai/&rft_pqid=2856971341&rft_id=info:pmid/&rft_galeid=A762478719&rfr_iscdi=true