A Preliminary Least Cost Model to Accomplish Explosive Phasedown

The report, details a simplified mathematical model that relates to the reduction of explosives manufactured in the most economical fashion during times of reduced demand. Because explosive manufacture is accomplished in production units termed lines, the probelm becomes one of integer programming....

Full description

Saved in:
Bibliographic Details
Main Author: Barnett,Bruce D
Format: Report
Language:English
Subjects:
Online Access:Request full text
Tags: Add Tag
No Tags, Be the first to tag this record!
Description
Summary:The report, details a simplified mathematical model that relates to the reduction of explosives manufactured in the most economical fashion during times of reduced demand. Because explosive manufacture is accomplished in production units termed lines, the probelm becomes one of integer programming. Additional constraints exist that limit the maximum number of line closings within a given time period. (Author)