Scheduling rules to minimize total tardiness in a parallel machine problem with setup and calendar constraints
Quality control lead times are one of most significant causes of loss of time in the pharmaceutical and cosmetics industries. This is partly due to the organization of laboratories that feature parallel multipurpose machines for chromatographic analyses. The testing process requires long setup times...
Saved in:
Published in: | Computers & operations research 2012-06, Vol.39 (6), p.1236-1244 |
---|---|
Main Authors: | , , , , |
Format: | Article |
Language: | English |
Subjects: | |
Citations: | Items that this one cites Items that cite this one |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | Quality control lead times are one of most significant causes of loss of time in the pharmaceutical and cosmetics industries. This is partly due to the organization of laboratories that feature parallel multipurpose machines for chromatographic analyses. The testing process requires long setup times and operators are needed to launch the process. The various controls are non-preemptive and are characterized by a release date, a due date and available routings. These quality processes lead to significant delays, and we therefore evaluate the total tardiness criterion. Previous heuristics were defined for the total tardiness criterion, parallel machines, and setup such as apparent tardiness cost (ATC) and ATC with setups (ATCS). We propose new rules and a simulated annealing procedure in order to minimize total tardiness. |
---|---|
ISSN: | 0305-0548 1873-765X 0305-0548 |
DOI: | 10.1016/j.cor.2010.07.007 |