Loading…
Project network models with discounted cash flows a guided tour through recent developments
The vast majority of the project scheduling methodologies presented in the literature have been developed with the objective of minimizing the project duration subject to precedence and other constraints. In doing so, the financial aspects of project management are largely ignored. Recent efforts ha...
Saved in:
Published in: | European journal of operational research 1997-07, Vol.100 (1), p.97-121 |
---|---|
Main Authors: | , , |
Format: | Article |
Language: | English |
Subjects: | |
Citations: | Items that this one cites Items that cite this one |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | The vast majority of the project scheduling methodologies presented in the literature have been developed with the objective of minimizing the project duration subject to precedence and other constraints. In doing so, the financial aspects of project management are largely ignored. Recent efforts have taken into account discounted cash flows and have focused on the maximization of the net present value (
npv) of the project as the more appropriate objective. In this paper we offer a guided tour through the important recent developments in the expanding field of research on deterministic and stochastic project network models with discounted cash flows. Subsequent to a close examination of the rationale behind the
npv objective, we offer a taxonomy of the problems studied in the literature and critically review the major contributions. Proper attention is given to
npv maximization models for the unconstrained scheduling problem with known cash flows, optimal and suboptimal scheduling procedures with various types of resource constraints, and the problem of determining both the timing and amount of payments. |
---|---|
ISSN: | 0377-2217 1872-6860 |
DOI: | 10.1016/S0377-2217(96)00112-9 |