Quantitative Analysis of the Factors Influencing Field Installation Time for Precast Concrete Building Components: An Empirical Study
Installation time for precast concrete (PC) components varies due to component-, location-, and weather-related factors. Because such variability affects the cost, time, and sustainability performance of PC projects, it is important to identify and classify the factors influencing installation time...
Saved in:
Published in: | Journal of management in engineering 2024-05, Vol.40 (3) |
---|---|
Main Authors: | , , , , |
Format: | Article |
Language: | English |
Subjects: | |
Citations: | Items that this one cites |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
cited_by | |
---|---|
cites | cdi_FETCH-LOGICAL-c279t-e9b06587c4b894a3376b87568af358f7875ddcf684ca9c0feb7ce224c778eb1d3 |
container_end_page | |
container_issue | 3 |
container_start_page | |
container_title | Journal of management in engineering |
container_volume | 40 |
creator | Jeong, Eunbeen Jang, Junyoung Lee, Seulbi Ahn, Seungjun Kim, Tae Wan |
description | Installation time for precast concrete (PC) components varies due to component-, location-, and weather-related factors. Because such variability affects the cost, time, and sustainability performance of PC projects, it is important to identify and classify the factors influencing installation time for different types of PC components. Against this background, this study aims to empirically investigate variability in installation time for PC components and different work steps and then identify the factors that affect particular work steps most significantly. To achieve the goal, this study gathered installation time and other influencing factors data from an actual project for 25 days and analyzed the data using a descriptive approach and the recursive feature elimination with cross-validation (RFECV) analysis. The analysis result provides empirical evidence that different PC types and work steps are involved with different levels of variability in installation time. The highest level of variability was shown in PC beams and assembly work. Regarding the factors influencing installation time, it is shown that different work steps are affected by different sets of influencing factors, with temperature and wind speed as the most common influencing factors across different PC types and work steps. This study contributes to the body of knowledge of off-site construction management by offering empirical evidence on the variability in PC installation time and the specific factors affecting PC installation time. |
doi_str_mv | 10.1061/JMENEA.MEENG-5816 |
format | article |
fullrecord | <record><control><sourceid>proquest_cross</sourceid><recordid>TN_cdi_proquest_journals_2930425664</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>2930425664</sourcerecordid><originalsourceid>FETCH-LOGICAL-c279t-e9b06587c4b894a3376b87568af358f7875ddcf684ca9c0feb7ce224c778eb1d3</originalsourceid><addsrcrecordid>eNotkN1KwzAUx4MoOKcP4F3A686kTZPWu1m6Odmm4gTvSpommtEmM0mFPYDvbee8OofD_4PzA-AaowlGFN8-rsp1OZ2synI9j9IM0xMwwjlJopSw_BSMECNxlObs_RxceL9FCMUM4RH4eem5CTrwoL8lnBre7r320CoYPiWccRGs83BhVNtLI7T5gDMt22a4-MDbdrBZAze6k1BZB5-dFNwHWFgjnAwS3ve6bQ6uwnY7a6QJ_m5ogWW3004L3sLX0Df7S3CmeOvl1f8cg7dZuSkeouXTfFFMl5GIWR4imdeIphkTpM5ywpOE0TpjKc24StJMsWFvGqFoRgTPBVKyZkLGMRGMZbLGTTIGN8fcnbNfvfSh2treDU_7Ks4TROKUUjKo8FElnPXeSVXtnO6421cYVQfa1ZF29Ue7OtBOfgEjPnXe</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>2930425664</pqid></control><display><type>article</type><title>Quantitative Analysis of the Factors Influencing Field Installation Time for Precast Concrete Building Components: An Empirical Study</title><source>ASCE Library (civil engineering)</source><creator>Jeong, Eunbeen ; Jang, Junyoung ; Lee, Seulbi ; Ahn, Seungjun ; Kim, Tae Wan</creator><creatorcontrib>Jeong, Eunbeen ; Jang, Junyoung ; Lee, Seulbi ; Ahn, Seungjun ; Kim, Tae Wan</creatorcontrib><description>Installation time for precast concrete (PC) components varies due to component-, location-, and weather-related factors. Because such variability affects the cost, time, and sustainability performance of PC projects, it is important to identify and classify the factors influencing installation time for different types of PC components. Against this background, this study aims to empirically investigate variability in installation time for PC components and different work steps and then identify the factors that affect particular work steps most significantly. To achieve the goal, this study gathered installation time and other influencing factors data from an actual project for 25 days and analyzed the data using a descriptive approach and the recursive feature elimination with cross-validation (RFECV) analysis. The analysis result provides empirical evidence that different PC types and work steps are involved with different levels of variability in installation time. The highest level of variability was shown in PC beams and assembly work. Regarding the factors influencing installation time, it is shown that different work steps are affected by different sets of influencing factors, with temperature and wind speed as the most common influencing factors across different PC types and work steps. This study contributes to the body of knowledge of off-site construction management by offering empirical evidence on the variability in PC installation time and the specific factors affecting PC installation time.</description><identifier>ISSN: 0742-597X</identifier><identifier>EISSN: 1943-5479</identifier><identifier>DOI: 10.1061/JMENEA.MEENG-5816</identifier><language>eng</language><publisher>New York: American Society of Civil Engineers</publisher><subject>Building components ; Construction management ; Empirical analysis ; Precast concrete ; Reinforced concrete ; Wind speed</subject><ispartof>Journal of management in engineering, 2024-05, Vol.40 (3)</ispartof><rights>2024 American Society of Civil Engineers</rights><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed><cites>FETCH-LOGICAL-c279t-e9b06587c4b894a3376b87568af358f7875ddcf684ca9c0feb7ce224c778eb1d3</cites><orcidid>0000-0002-7137-1832 ; 0000-0001-7427-8986 ; 0009-0003-1285-1494 ; 0000-0002-7887-1055</orcidid></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><link.rule.ids>314,780,784,3252,27924,27925</link.rule.ids></links><search><creatorcontrib>Jeong, Eunbeen</creatorcontrib><creatorcontrib>Jang, Junyoung</creatorcontrib><creatorcontrib>Lee, Seulbi</creatorcontrib><creatorcontrib>Ahn, Seungjun</creatorcontrib><creatorcontrib>Kim, Tae Wan</creatorcontrib><title>Quantitative Analysis of the Factors Influencing Field Installation Time for Precast Concrete Building Components: An Empirical Study</title><title>Journal of management in engineering</title><description>Installation time for precast concrete (PC) components varies due to component-, location-, and weather-related factors. Because such variability affects the cost, time, and sustainability performance of PC projects, it is important to identify and classify the factors influencing installation time for different types of PC components. Against this background, this study aims to empirically investigate variability in installation time for PC components and different work steps and then identify the factors that affect particular work steps most significantly. To achieve the goal, this study gathered installation time and other influencing factors data from an actual project for 25 days and analyzed the data using a descriptive approach and the recursive feature elimination with cross-validation (RFECV) analysis. The analysis result provides empirical evidence that different PC types and work steps are involved with different levels of variability in installation time. The highest level of variability was shown in PC beams and assembly work. Regarding the factors influencing installation time, it is shown that different work steps are affected by different sets of influencing factors, with temperature and wind speed as the most common influencing factors across different PC types and work steps. This study contributes to the body of knowledge of off-site construction management by offering empirical evidence on the variability in PC installation time and the specific factors affecting PC installation time.</description><subject>Building components</subject><subject>Construction management</subject><subject>Empirical analysis</subject><subject>Precast concrete</subject><subject>Reinforced concrete</subject><subject>Wind speed</subject><issn>0742-597X</issn><issn>1943-5479</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2024</creationdate><recordtype>article</recordtype><recordid>eNotkN1KwzAUx4MoOKcP4F3A686kTZPWu1m6Odmm4gTvSpommtEmM0mFPYDvbee8OofD_4PzA-AaowlGFN8-rsp1OZ2synI9j9IM0xMwwjlJopSw_BSMECNxlObs_RxceL9FCMUM4RH4eem5CTrwoL8lnBre7r320CoYPiWccRGs83BhVNtLI7T5gDMt22a4-MDbdrBZAze6k1BZB5-dFNwHWFgjnAwS3ve6bQ6uwnY7a6QJ_m5ogWW3004L3sLX0Df7S3CmeOvl1f8cg7dZuSkeouXTfFFMl5GIWR4imdeIphkTpM5ywpOE0TpjKc24StJMsWFvGqFoRgTPBVKyZkLGMRGMZbLGTTIGN8fcnbNfvfSh2treDU_7Ks4TROKUUjKo8FElnPXeSVXtnO6421cYVQfa1ZF29Ue7OtBOfgEjPnXe</recordid><startdate>20240501</startdate><enddate>20240501</enddate><creator>Jeong, Eunbeen</creator><creator>Jang, Junyoung</creator><creator>Lee, Seulbi</creator><creator>Ahn, Seungjun</creator><creator>Kim, Tae Wan</creator><general>American Society of Civil Engineers</general><scope>AAYXX</scope><scope>CITATION</scope><scope>7TA</scope><scope>7TB</scope><scope>8FD</scope><scope>FR3</scope><scope>JG9</scope><scope>KR7</scope><orcidid>https://orcid.org/0000-0002-7137-1832</orcidid><orcidid>https://orcid.org/0000-0001-7427-8986</orcidid><orcidid>https://orcid.org/0009-0003-1285-1494</orcidid><orcidid>https://orcid.org/0000-0002-7887-1055</orcidid></search><sort><creationdate>20240501</creationdate><title>Quantitative Analysis of the Factors Influencing Field Installation Time for Precast Concrete Building Components: An Empirical Study</title><author>Jeong, Eunbeen ; Jang, Junyoung ; Lee, Seulbi ; Ahn, Seungjun ; Kim, Tae Wan</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c279t-e9b06587c4b894a3376b87568af358f7875ddcf684ca9c0feb7ce224c778eb1d3</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2024</creationdate><topic>Building components</topic><topic>Construction management</topic><topic>Empirical analysis</topic><topic>Precast concrete</topic><topic>Reinforced concrete</topic><topic>Wind speed</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Jeong, Eunbeen</creatorcontrib><creatorcontrib>Jang, Junyoung</creatorcontrib><creatorcontrib>Lee, Seulbi</creatorcontrib><creatorcontrib>Ahn, Seungjun</creatorcontrib><creatorcontrib>Kim, Tae Wan</creatorcontrib><collection>CrossRef</collection><collection>Materials Business File</collection><collection>Mechanical & Transportation Engineering Abstracts</collection><collection>Technology Research Database</collection><collection>Engineering Research Database</collection><collection>Materials Research Database</collection><collection>Civil Engineering Abstracts</collection><jtitle>Journal of management in engineering</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Jeong, Eunbeen</au><au>Jang, Junyoung</au><au>Lee, Seulbi</au><au>Ahn, Seungjun</au><au>Kim, Tae Wan</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Quantitative Analysis of the Factors Influencing Field Installation Time for Precast Concrete Building Components: An Empirical Study</atitle><jtitle>Journal of management in engineering</jtitle><date>2024-05-01</date><risdate>2024</risdate><volume>40</volume><issue>3</issue><issn>0742-597X</issn><eissn>1943-5479</eissn><abstract>Installation time for precast concrete (PC) components varies due to component-, location-, and weather-related factors. Because such variability affects the cost, time, and sustainability performance of PC projects, it is important to identify and classify the factors influencing installation time for different types of PC components. Against this background, this study aims to empirically investigate variability in installation time for PC components and different work steps and then identify the factors that affect particular work steps most significantly. To achieve the goal, this study gathered installation time and other influencing factors data from an actual project for 25 days and analyzed the data using a descriptive approach and the recursive feature elimination with cross-validation (RFECV) analysis. The analysis result provides empirical evidence that different PC types and work steps are involved with different levels of variability in installation time. The highest level of variability was shown in PC beams and assembly work. Regarding the factors influencing installation time, it is shown that different work steps are affected by different sets of influencing factors, with temperature and wind speed as the most common influencing factors across different PC types and work steps. This study contributes to the body of knowledge of off-site construction management by offering empirical evidence on the variability in PC installation time and the specific factors affecting PC installation time.</abstract><cop>New York</cop><pub>American Society of Civil Engineers</pub><doi>10.1061/JMENEA.MEENG-5816</doi><orcidid>https://orcid.org/0000-0002-7137-1832</orcidid><orcidid>https://orcid.org/0000-0001-7427-8986</orcidid><orcidid>https://orcid.org/0009-0003-1285-1494</orcidid><orcidid>https://orcid.org/0000-0002-7887-1055</orcidid></addata></record> |
fulltext | fulltext |
identifier | ISSN: 0742-597X |
ispartof | Journal of management in engineering, 2024-05, Vol.40 (3) |
issn | 0742-597X 1943-5479 |
language | eng |
recordid | cdi_proquest_journals_2930425664 |
source | ASCE Library (civil engineering) |
subjects | Building components Construction management Empirical analysis Precast concrete Reinforced concrete Wind speed |
title | Quantitative Analysis of the Factors Influencing Field Installation Time for Precast Concrete Building Components: An Empirical Study |
url | http://sfxeu10.hosted.exlibrisgroup.com/loughborough?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-27T19%3A03%3A35IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Quantitative%20Analysis%20of%20the%20Factors%20Influencing%20Field%20Installation%20Time%20for%20Precast%20Concrete%20Building%20Components:%20An%20Empirical%20Study&rft.jtitle=Journal%20of%20management%20in%20engineering&rft.au=Jeong,%20Eunbeen&rft.date=2024-05-01&rft.volume=40&rft.issue=3&rft.issn=0742-597X&rft.eissn=1943-5479&rft_id=info:doi/10.1061/JMENEA.MEENG-5816&rft_dat=%3Cproquest_cross%3E2930425664%3C/proquest_cross%3E%3Cgrp_id%3Ecdi_FETCH-LOGICAL-c279t-e9b06587c4b894a3376b87568af358f7875ddcf684ca9c0feb7ce224c778eb1d3%3C/grp_id%3E%3Coa%3E%3C/oa%3E%3Curl%3E%3C/url%3E&rft_id=info:oai/&rft_pqid=2930425664&rft_id=info:pmid/&rfr_iscdi=true |