The effect of power utility right-of-way construction on cat-tail (Typha latifolia L.) marsh
Vegetation in an eastern Massachusetts freshwater cat-tail marsh was measured over a five-year period, two years before and three years after construction of a 345 kv transmission line; no change in vegetation occurred because of the construction.
Saved in:
Published in: | Rhodora 1984-01, Vol.86 (847), p.389-391 |
---|---|
Main Authors: | , |
Format: | Article |
Language: | English |
Subjects: | |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | Vegetation in an eastern Massachusetts freshwater cat-tail marsh was measured over a five-year period, two years before and three years after construction of a 345 kv transmission line; no change in vegetation occurred because of the construction. |
---|---|