Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey
AbstractConstruction delays are common in construction industry and create major concerns for project performance. Construction delays are caused by many factors. The aim of this paper is to identify delay factors on construction projects and analyze these factors with the relative importance index...
Saved in:
Published in: | Journal of management in engineering 2013-04, Vol.29 (2), p.133-139 |
---|---|
Main Authors: | , , |
Format: | Article |
Language: | English |
Subjects: | |
Citations: | Items that this one cites Items that cite this one |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
cited_by | cdi_FETCH-LOGICAL-a464t-e91111db548a26cdfddbb1379f7356c3f3b7bd91433570db399f847f810fa4e03 |
---|---|
cites | cdi_FETCH-LOGICAL-a464t-e91111db548a26cdfddbb1379f7356c3f3b7bd91433570db399f847f810fa4e03 |
container_end_page | 139 |
container_issue | 2 |
container_start_page | 133 |
container_title | Journal of management in engineering |
container_volume | 29 |
creator | Gündüz, Murat Nielsen, Yasemin Özdemir, Mustafa |
description | AbstractConstruction delays are common in construction industry and create major concerns for project performance. Construction delays are caused by many factors. The aim of this paper is to identify delay factors on construction projects and analyze these factors with the relative importance index method. For this purpose, 83 different delay factors were identified, categorized into nine major groups, and visualized by the Ishikawa (fishbone) diagram through detailed literature review and interviews with experts from the construction industry. The relative importances of these delay factors were quantified by the relative importance index method. The ranking of the factors and groups were demonstrated according to their importance level on delay. According to the case study results, the factors and groups contributing the most to delays (those needing attention) were discussed, and some recommendations were made to minimize and control delays in construction projects. |
doi_str_mv | 10.1061/(ASCE)ME.1943-5479.0000129 |
format | article |
fullrecord | <record><control><sourceid>proquest_cross</sourceid><recordid>TN_cdi_proquest_miscellaneous_1864527228</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>1864527228</sourcerecordid><originalsourceid>FETCH-LOGICAL-a464t-e91111db548a26cdfddbb1379f7356c3f3b7bd91433570db399f847f810fa4e03</originalsourceid><addsrcrecordid>eNp1kEtPAyEUhYnRxPr4D8RVXUyFgRkGd6a2atLGd-KOMAzYqS1UYIz991LbuPNu7s3JOSe5HwBnGA0wKvFF_-p5ODqfjgaYU5IVlPEBSoNzvgd6f9o-6CFG86zg7O0QHIUwT56cIdwD9rGTNramVTK2zkJn4LVeyDUcSxWdD_A1tPYdxpmGT0mP7ZeGd8uV81FalU7b6G841XHmGmich0NnQ_Sd-i178G6uVQywtfCl8x96fQIOjFwEfbrbx-B1PHoZ3maT-5u74dUkk7SkMdMcp2nqglYyL1VjmqauMWHcMFKUihhSs7rhmBJSMNTUhHNTUWYqjIykGpFj0N_2rrz77HSIYtkGpRcLabXrgsBVSYuc5XmVrJdbq_IuBK-NWPl2Kf1aYCQ2kIXYQBbTkdgAFRugYgc5hcttWKZ2MXedt-mtv-T_wR8SH4JX</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>1864527228</pqid></control><display><type>article</type><title>Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey</title><source>ASCE_美国土木工程师学会期刊</source><source>Business Source Ultimate</source><creator>Gündüz, Murat ; Nielsen, Yasemin ; Özdemir, Mustafa</creator><creatorcontrib>Gündüz, Murat ; Nielsen, Yasemin ; Özdemir, Mustafa</creatorcontrib><description>AbstractConstruction delays are common in construction industry and create major concerns for project performance. Construction delays are caused by many factors. The aim of this paper is to identify delay factors on construction projects and analyze these factors with the relative importance index method. For this purpose, 83 different delay factors were identified, categorized into nine major groups, and visualized by the Ishikawa (fishbone) diagram through detailed literature review and interviews with experts from the construction industry. The relative importances of these delay factors were quantified by the relative importance index method. The ranking of the factors and groups were demonstrated according to their importance level on delay. According to the case study results, the factors and groups contributing the most to delays (those needing attention) were discussed, and some recommendations were made to minimize and control delays in construction projects.</description><identifier>ISSN: 0742-597X</identifier><identifier>EISSN: 1943-5479</identifier><identifier>DOI: 10.1061/(ASCE)ME.1943-5479.0000129</identifier><language>eng</language><publisher>American Society of Civil Engineers</publisher><subject>Construction industry ; Construction methods ; Delay ; Literature reviews ; Management ; Performance indices ; Ranking ; Recommendations ; Technical Papers</subject><ispartof>Journal of management in engineering, 2013-04, Vol.29 (2), p.133-139</ispartof><rights>2013 American Society of Civil Engineers</rights><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed><citedby>FETCH-LOGICAL-a464t-e91111db548a26cdfddbb1379f7356c3f3b7bd91433570db399f847f810fa4e03</citedby><cites>FETCH-LOGICAL-a464t-e91111db548a26cdfddbb1379f7356c3f3b7bd91433570db399f847f810fa4e03</cites></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktopdf>$$Uhttp://ascelibrary.org/doi/pdf/10.1061/(ASCE)ME.1943-5479.0000129$$EPDF$$P50$$Gasce$$H</linktopdf><linktohtml>$$Uhttp://ascelibrary.org/doi/abs/10.1061/(ASCE)ME.1943-5479.0000129$$EHTML$$P50$$Gasce$$H</linktohtml><link.rule.ids>314,780,784,3250,10067,27923,27924,75962,75970</link.rule.ids></links><search><creatorcontrib>Gündüz, Murat</creatorcontrib><creatorcontrib>Nielsen, Yasemin</creatorcontrib><creatorcontrib>Özdemir, Mustafa</creatorcontrib><title>Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey</title><title>Journal of management in engineering</title><description>AbstractConstruction delays are common in construction industry and create major concerns for project performance. Construction delays are caused by many factors. The aim of this paper is to identify delay factors on construction projects and analyze these factors with the relative importance index method. For this purpose, 83 different delay factors were identified, categorized into nine major groups, and visualized by the Ishikawa (fishbone) diagram through detailed literature review and interviews with experts from the construction industry. The relative importances of these delay factors were quantified by the relative importance index method. The ranking of the factors and groups were demonstrated according to their importance level on delay. According to the case study results, the factors and groups contributing the most to delays (those needing attention) were discussed, and some recommendations were made to minimize and control delays in construction projects.</description><subject>Construction industry</subject><subject>Construction methods</subject><subject>Delay</subject><subject>Literature reviews</subject><subject>Management</subject><subject>Performance indices</subject><subject>Ranking</subject><subject>Recommendations</subject><subject>Technical Papers</subject><issn>0742-597X</issn><issn>1943-5479</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2013</creationdate><recordtype>article</recordtype><recordid>eNp1kEtPAyEUhYnRxPr4D8RVXUyFgRkGd6a2atLGd-KOMAzYqS1UYIz991LbuPNu7s3JOSe5HwBnGA0wKvFF_-p5ODqfjgaYU5IVlPEBSoNzvgd6f9o-6CFG86zg7O0QHIUwT56cIdwD9rGTNramVTK2zkJn4LVeyDUcSxWdD_A1tPYdxpmGT0mP7ZeGd8uV81FalU7b6G841XHmGmich0NnQ_Sd-i178G6uVQywtfCl8x96fQIOjFwEfbrbx-B1PHoZ3maT-5u74dUkk7SkMdMcp2nqglYyL1VjmqauMWHcMFKUihhSs7rhmBJSMNTUhHNTUWYqjIykGpFj0N_2rrz77HSIYtkGpRcLabXrgsBVSYuc5XmVrJdbq_IuBK-NWPl2Kf1aYCQ2kIXYQBbTkdgAFRugYgc5hcttWKZ2MXedt-mtv-T_wR8SH4JX</recordid><startdate>20130401</startdate><enddate>20130401</enddate><creator>Gündüz, Murat</creator><creator>Nielsen, Yasemin</creator><creator>Özdemir, Mustafa</creator><general>American Society of Civil Engineers</general><scope>AAYXX</scope><scope>CITATION</scope><scope>7TA</scope><scope>7TB</scope><scope>8FD</scope><scope>F28</scope><scope>FR3</scope><scope>JG9</scope><scope>KR7</scope></search><sort><creationdate>20130401</creationdate><title>Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey</title><author>Gündüz, Murat ; Nielsen, Yasemin ; Özdemir, Mustafa</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-a464t-e91111db548a26cdfddbb1379f7356c3f3b7bd91433570db399f847f810fa4e03</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2013</creationdate><topic>Construction industry</topic><topic>Construction methods</topic><topic>Delay</topic><topic>Literature reviews</topic><topic>Management</topic><topic>Performance indices</topic><topic>Ranking</topic><topic>Recommendations</topic><topic>Technical Papers</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Gündüz, Murat</creatorcontrib><creatorcontrib>Nielsen, Yasemin</creatorcontrib><creatorcontrib>Özdemir, Mustafa</creatorcontrib><collection>CrossRef</collection><collection>Materials Business File</collection><collection>Mechanical & Transportation Engineering Abstracts</collection><collection>Technology Research Database</collection><collection>ANTE: Abstracts in New Technology & Engineering</collection><collection>Engineering Research Database</collection><collection>Materials Research Database</collection><collection>Civil Engineering Abstracts</collection><jtitle>Journal of management in engineering</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Gündüz, Murat</au><au>Nielsen, Yasemin</au><au>Özdemir, Mustafa</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey</atitle><jtitle>Journal of management in engineering</jtitle><date>2013-04-01</date><risdate>2013</risdate><volume>29</volume><issue>2</issue><spage>133</spage><epage>139</epage><pages>133-139</pages><issn>0742-597X</issn><eissn>1943-5479</eissn><abstract>AbstractConstruction delays are common in construction industry and create major concerns for project performance. Construction delays are caused by many factors. The aim of this paper is to identify delay factors on construction projects and analyze these factors with the relative importance index method. For this purpose, 83 different delay factors were identified, categorized into nine major groups, and visualized by the Ishikawa (fishbone) diagram through detailed literature review and interviews with experts from the construction industry. The relative importances of these delay factors were quantified by the relative importance index method. The ranking of the factors and groups were demonstrated according to their importance level on delay. According to the case study results, the factors and groups contributing the most to delays (those needing attention) were discussed, and some recommendations were made to minimize and control delays in construction projects.</abstract><pub>American Society of Civil Engineers</pub><doi>10.1061/(ASCE)ME.1943-5479.0000129</doi><tpages>7</tpages></addata></record> |
fulltext | fulltext |
identifier | ISSN: 0742-597X |
ispartof | Journal of management in engineering, 2013-04, Vol.29 (2), p.133-139 |
issn | 0742-597X 1943-5479 |
language | eng |
recordid | cdi_proquest_miscellaneous_1864527228 |
source | ASCE_美国土木工程师学会期刊; Business Source Ultimate |
subjects | Construction industry Construction methods Delay Literature reviews Management Performance indices Ranking Recommendations Technical Papers |
title | Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey |
url | http://sfxeu10.hosted.exlibrisgroup.com/loughborough?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-11T13%3A23%3A41IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Quantification%20of%20Delay%20Factors%20Using%20the%20Relative%20Importance%20Index%20Method%20for%20Construction%20Projects%20in%20Turkey&rft.jtitle=Journal%20of%20management%20in%20engineering&rft.au=G%C3%BCnd%C3%BCz,%20Murat&rft.date=2013-04-01&rft.volume=29&rft.issue=2&rft.spage=133&rft.epage=139&rft.pages=133-139&rft.issn=0742-597X&rft.eissn=1943-5479&rft_id=info:doi/10.1061/(ASCE)ME.1943-5479.0000129&rft_dat=%3Cproquest_cross%3E1864527228%3C/proquest_cross%3E%3Cgrp_id%3Ecdi_FETCH-LOGICAL-a464t-e91111db548a26cdfddbb1379f7356c3f3b7bd91433570db399f847f810fa4e03%3C/grp_id%3E%3Coa%3E%3C/oa%3E%3Curl%3E%3C/url%3E&rft_id=info:oai/&rft_pqid=1864527228&rft_id=info:pmid/&rfr_iscdi=true |