Loading…
The Rockport plant-analysis of temporary fast turbine valving tests
Temporary fast turbine valving (TFTV) field tests were carried out on AEP's 1300 MW Rockport unit. Tests at various unit loading levels verified the functional aspects of the TFTV scheme, including the control and intercept valve-stroke characteristics and the rapid reduction of mechanical driv...
Saved in:
Published in: | IEEE transactions on power systems 1988-05, Vol.3 (2), p.529-540 |
---|---|
Main Authors: | , |
Format: | Article |
Language: | English |
Subjects: | |
Citations: | Items that this one cites Items that cite this one |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | Temporary fast turbine valving (TFTV) field tests were carried out on AEP's 1300 MW Rockport unit. Tests at various unit loading levels verified the functional aspects of the TFTV scheme, including the control and intercept valve-stroke characteristics and the rapid reduction of mechanical driving power. An analysis of the mechanical and electrical performance characteristics of the Rockport unit during TFTV is presented. A comparison of the test measurements with digital simulation results is provided to validate the simulation tools and models commonly used in system dynamics studies.< > |
---|---|
ISSN: | 0885-8950 1558-0679 |