Describes how the transverse passages, the pumping station and the railway crossover were constructed. 187 cross-passages and piston relief ducts were driven. The pumping station, designed to dewater the tunnels, was built 8.8 km from the Sangatte shaft. The railway crossover, which allows the linki...
Saved in:
Published in: | Proceedings of the Institution of Civil Engineers. Civil engineering 1994-01, Vol.102 (5), p.63-75 |
---|---|
Main Authors: | , , , , , , , , , , , , |
Format: | Article |
Language: | English |
Online Access: | Get full text |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | Describes how the transverse passages, the pumping station and the railway crossover were constructed. 187 cross-passages and piston relief ducts were driven. The pumping station, designed to dewater the tunnels, was built 8.8 km from the Sangatte shaft. The railway crossover, which allows the linking of the north and south tracks, was excavated open face. |
---|---|
ISSN: | 0965-089X 1751-7672 |
DOI: | 10.1680/icien.1994.26814 |